Decision Notice

On , the Financial Conduct Authority issued a Decision Notice to Richard John Howson
1

DECISION NOTICE

1.
ACTION

1.1.
For the reasons given in this Decision Notice, the Authority has decided to impose

on Richard Howson a financial penalty of £397,800 pursuant to:

(1)
Section 123 (power to impose penalties in cases of market abuse); and

(2)
Section 91 (penalties for breach of Part 6 rules)

of the Financial Services and Markets Act 2000.

1.2.
The Authority has decided to impose the aforementioned financial penalty on Mr

Howson for being knowingly concerned in breaches by Carillion plc of:

(1)
Article 15 of MAR (prohibition of market manipulation);

(2)
Listing Rule 1.3.3R (misleading information must not be published);

(3)
Listing Principle 1 (procedures, systems and controls); and

(4)
Premium Listing Principle 2 (acting with integrity).

This decision notice has been referred to the Upper Tribunal to determine what
(if any) the appropriate action is for the Authority to take, and remit the matter
to the Authority with such directions as the Tribunal considers appropriate.

2

2.
SUMMARY OF REASONS

2.1.
Carillion was, until it went into liquidation in January 2018, a leading international

construction, project finance and support services business operating in the UK,

Canada and Middle East.

2.2.
On 10 July 2017, Carillion announced (amongst other things) an expected

provision of £845 million as at 30 July 2017, of which £375 million was in relation

to projects in Carillion Construction Services (CCS). The provision arose from a

review following a deterioration in cash flows across several construction projects,

including within the UK.

2.3.
The nature of the required provision surprised market analysts and Carillion’s

share price fell by 39% on the day of the announcement and by 70% within three

days. Carillion subsequently went into liquidation on 15 January 2018.

2.4.
The market’s adverse reaction resulted from the unexpected nature and size of

the provision, which effectively wiped out Carillion’s profits over the previous six

years. Carillion’s previous announcements, specifically its trading update on 7

December 2016, its 2016 financial results published on 1 March 2017 and its AGM

statement on 3 May 2017, had given no indication to the market that such a

provision was likely to be required.

2.5.
Such previous announcements were misleading and were made recklessly. They

did not accurately or fully disclose the true financial performance of Carillion. They

made positive statements about Carillion’s financial performance generally and in

relation to CCS’s construction business segment in particular. They failed to

disclose significant deteriorations in the expected performance of projects across

the CCS portfolio and did not take account of a series of warning signs indicating

anticipated losses and/or reduced profitability across a number of major

construction projects. It was these matters that, when eventually acknowledged

by Carillion, led to a significant proportion of the provision announced in July 2017.

2.6.
Mr Howson was Carillion’s Group Chief Executive Officer from 1 January 2012 to

10 July 2017. This Notice relates to Mr Howson’s conduct as Group CEO between

1 July 2016 and 10 July 2017 (the Relevant Period).

3

2.7.
During the Relevant Period, Mr Howson, as Group CEO, was one of two executive

directors on Carillion’s Board. His responsibilities included working closely with

the Group Finance Director (the other executive director on the Board) to ensure

Carillion communicated effectively with investors and had appropriate internal

control processes.

Overly aggressive contract accounting judgements and internal reporting to Mr

2.8.
There was significant pressure on CCS during the Relevant Period to meet very

challenging financial targets maintained by Mr Howson (along with other senior

management) in the face of clear warning signs that CCS’s business was

deteriorating significantly. This led to an increasingly large gap between the

assessments within CCS of its financial performance and its performance as

budgeted and ultimately reported to the market.

2.9.
This gap was bridged during the Relevant Period by the use of overly aggressive

contract accounting judgements in order to maintain CCS’s reported revenues and

profitability, especially in connection with certain major construction projects.

These judgements did not reflect the true financial position of the projects or the

financial risks associated with them. They did not comply with IAS 11, one of the

applicable accounting standards governing the recognition of revenue associated

with construction contracts.

2.10.
CCS’s management highlighted the financial risks and exposures associated with

these judgements to Mr Howson and others during the Relevant Period. In

particular:

(1)
CCS internally reported “hard risks” associated with its construction

projects. These were amounts included within budgeted forecasts, but

which were considered by CCS management as unlikely to be recovered. In

August and October 2016, hard risks within CCS were reported to Mr Howson

and others as amounting to around £172 million. By April 2017, Mr Howson

knew this figure had increased to just over £310 million.

(2)
CCS, along with other Business Divisions within Carillion, reported potential

exposures to amounts due on major projects. This was contained in a report

known as the Major Contracts Summary (MCS). By October 2016, the total

amount due to CCS that was considered to be contentious was just under

£244 million, with a “likely” exposure of around £173 million (i.e. 71% of

the contentious amounts due) and 11 out of 16 named major projects

marked with a red flag status. This was reported to Mr Howson and others.

By May 2017, according to an MCS dated 4 May 2017 received by Mr

Howson, the likely exposure figure had increased to over £430 million (71%

of the contentious amounts due).

(3)
Large and increasing divergences in financial performance were highlighted

to Mr Howson and others during the Relevant Period in relation to four major

projects: Royal Liverpool University Hospital (RLUH), Phase 1 Battersea

Power Station redevelopment (Battersea), Midland Metropolitan Hospital

(MMH) and Aberdeen Western Peripheral Route (AWPR). This made clear

that there was an increasingly large disparity for those projects between the

assessments of financial performance by project and/or management teams

within CCS and the financial performance as reflected in Carillion’s budgeted

forecasts. The following gaps were highlighted to Mr Howson and others

during the Relevant Period:

a.
RLUH: A £21 million loss (assessed by the relevant Project Team)

against a budgeted forecast profit of £13.6 million by December 2016,

a difference of almost £35 million. This difference increased to £72

million by April 2017 as RLUH’s financial performance deteriorated;

b.
Battersea: A £25 million loss (assessed by the relevant Project Team)

against a budgeted forecast profit of around £10 million by December

2016, a difference of £35 million. This gap rose to over £43 million by

April 2017;

c.
MMH: A £15.7 million loss (assessed by the relevant Project Team)

against a budgeted forecast profit of £17.7 million by April 2017, a

difference of over £33 million; and

d.
AWPR: A £78 million loss (assessed by the relevant Business Unit

within CCS) against a budgeted forecast loss of £10 million by

December 2016, a difference of £68 million. This increased to a gap of

over £85 million by April 2017.

2.11.
When Carillion made its provision in July 2017, a total of £240 million was

provided against the above four projects, consistent with the amounts noted

5

above. This represented almost two-thirds of CCS’s total provision of £375

million.

Reporting to the Board and the Audit Committee

2.12.
Mr Howson, as Group CEO, reported to the Board on a monthly basis and attended

Audit Committee meetings during the Relevant Period.

2.13.
The financial risks and exposures described at paragraph 2.10 above were not

reported by Mr Howson (or otherwise to his knowledge) to the Board or the Audit

Committee. The key information received by the Board and the Audit Committee

in relation to the financial performance of CCS and its major projects during the

Relevant Period was in the form of a monthly Overtrade Report and a quarterly

Major Project Status Report (MPSR). They were also informed about the level of

provisions applied to Carillion’s major contracts (which, prior to the £845 million

provision announced on 10 July 2017, totalled £50.1 million for the whole of

Carillion’s business). At half and full year Mr Howson, as Group CEO, would attend

the Audit Committee, where a report was provided by the Group FD which

included a summary of financial risks and key judgements associated with major

projects.

2.14.
As Mr Howson was aware, these reports to the Board and the Audit Committee

painted a much more optimistic picture of CCS’s financial performance than that

being internally reported by CCS. As stated in paragraph 2.10(2) above, the MCS

in October 2016 (which the Board and the Audit Committee did not see) was

identifying a likely exposure of £173 million. In contrast, the Overtrade Report

did not show what those within CCS thought were likely exposures; instead, it

showed revenue “traded not certified” (i.e. amounts that had not yet been agreed

with the client which the Overtrade Report reported as appropriate to recognise

as revenue). Throughout the Relevant Period up to February 2017, it reported

this revenue at between £42 million and £44 million.

2.15.
The MPSR was aligned, to Mr Howson’s knowledge during the Relevant Period, to

the budgeted and reforecast figures and did not disclose increasing variances

between these figures and the Project Team’s or Business Unit’s assessments of

RLUH, Battersea, MMH and AWPR. It did not show any material deterioration in

CCS’s major projects during the Relevant Period. The Group FD’s report for the

2016 full year similarly did not identify any material deterioration associated with

major projects.

6

2.16.
Before the announcement in July 2017, the amount of provisions in Carillion’s

monthly management accounts for CCS’s projects remained broadly unchanged

at up to £17 million for all risks.

The Announcements

2.17.
The December Announcement made positive statements that Carillion’s

performance was “meeting expectations”, with expectations for “strong growth in

total revenue and increased operating profit” for the Group and “operating

margin” for Construction Services (excluding Middle East)1 remaining within a

target range of 2.5-3% for the 2016 year-end. It described Carillion as “well

positioned to make further progress in 2017”.

2.18.
These positive statements were not justified. They did not reflect the true

financial performance of CCS’s construction contracts and the December

Announcement omitted any reference to the significant risks associated with these

stated expectations that had arisen as at the date of this announcement, including

a number of the hard risks, exposures and divergences described at paragraph

2.10 above.

2.19.
The March Results Announcement made similar positive statements to those in

the December Announcement. In particular, it described Carillion’s performance

as “in line with expectations”, with revenue growth for the Group of 11% and

underlying profit before tax (PBT) of £178 million. The document published

alongside (and linked from) the March Results Announcement stated that

“Revenue grew strongly by 21 per cent” in Construction Services (excluding the

Middle East) and confirmed that operating margin for this segment “remains

within our target range of 2.5 per cent to 3 per cent”. It described the ambition

for this segment in 2017 as being “to maintain revenue and profit at broadly their

current levels”. The March Results Announcement went on to refer to Carillion

having a “good platform from which to develop the business in 2017”.

2.20.
The March Results Announcement was misleading because the above statements

concerning the financial performance of Carillion and Construction Services

(excluding the Middle East) for 2016 and stated expectations for 2017 did not

reflect the true performance of CCS’s construction contracts and the

announcement omitted any reference to the significant risks associated with these

1 The business segment of Construction Services (excluding the Middle East) included CCS’s construction
business

7

stated expectations as described at paragraph 2.10 above. The revenue and profit

/ margin figures for the Group and Construction Services (excluding the Middle

East) in the March Results Announcement were misstated because they did not

accurately reflect the financial performance of RLUH, Battersea, MMH and AWPR.

In particular, Carillion failed to recognise the costs and revenue associated with

these projects in accordance with IAS 11. The revenue and profit / margin figures

were materially overstated as a result. The positive statements for 2017 for Group

and Construction Services (excluding the Middle East) were similarly not justified

because they did not take account of matters arising before this date, as described

at paragraph 2.10 above.

2.21.
The tenor of the May Announcement was that nothing had materially changed

since the March Results Announcement. This was reflected in its heading

(“Trading conditions unchanged”) and opening sentence (“Trading conditions

across the Group’s markets have remained largely unchanged since we announced

our 2016 full-year results”). This was not an accurate depiction of the Group’s

trading as at 3 May 2017, which was materially affected by the adverse and

deteriorating financial performance of CCS’s construction projects as at the date

of this announcement, as described at paragraph 2.10 above.

2.22.
Mr Howson as Group CEO and one of only two executive directors had a central

role in reviewing the Announcements and approving them as a Board member.

He did so in the knowledge of information reported to him on a number of

occasions and summarised at paragraph 2.10 above that was materially

inconsistent with the positive statements made in the Announcements. Mr

Howson must have been aware, particularly having regard to the nature and

cumulative effect of the information and the occasions on which it was reported

to him, and his extensive knowledge of the construction industry, that this

information would be highly relevant to the deliberations of the Board and the

Audit Committee when they reviewed and approved the Announcements.

However, Mr Howson failed to ensure that this information was brought to the

attention of the Board and the Audit Committee.

2.23.
In light of the above, the Authority considers that Carillion disseminated

information in the Announcements that gave false or misleading signals as to the

value of its shares in circumstances where it ought to have known that the

information was false or misleading, in breach of Article 15 of MAR, and that Mr

Howson was knowingly concerned in Carillion’s breach of Article 15 of MAR.

2.24.
During the Relevant Period, Mr Howson was aware that Carillion intended to

announce a PBT figure of £178 million in its 2016 financial results. He was also

aware that this PBT figure included financial reporting for RLUH, Battersea and

AWPR that was aligned with the budgeted forecast figures at paragraph 2.10(3)

above. Mr Howson did not take any steps during the Relevant Period to address

the material inconsistencies between (i) the proposed PBT figure and financial

reporting for RLUH, Battersea and AWPR and (ii) other information of which he

was aware (see paragraphs 2.14 and 2.15 above). He also failed to ensure that

these matters were brought to the attention of the Board and the Audit

Committee.

2.25.
In light of the above, and the matters summarised at paragraphs 2.26 to 2.31

below in relation to Listing Principle 1, the Authority considers that Carillion failed

to take reasonable care during the Relevant Period to ensure that the

Announcements were not misleading, false or deceptive and did not omit anything

likely to affect the import of the information, in breach of LR 1.3.3R, and that Mr

Howson was knowingly concerned in Carillion’s breach of LR 1.3.3R.

Procedures, systems & controls

2.26.
The deterioration in CCS’s business during the Relevant Period, coupled with the

pressure to meet very challenging financial targets, significantly increased the risk

that overly aggressive contract accounting judgements would be applied in order

to maintain its financial performance. To counter this risk, Carillion’s procedures,

systems and controls in relation to CCS needed to be sufficiently robust to ensure

that these judgements were made and reported appropriately. They were not,

significantly increasing the risk that market announcements in relation to

Carillion’s financial performance would not be accurate.

2.27.
The overly aggressive contract accounting judgements being applied to CCS’s

major projects were not properly documented at Performance Review Meetings

held by CCS (which Mr Howson chaired). This meant there was no clear record of

the assessments being made, approved or reviewed. This contributed to a lack

of rigour around these judgements and their approval and review.

2.28.
The management information relating to hard risks, MCSs and certain major

projects produced and reported by CCS to (amongst others) Mr Howson

highlighted large and increasing risks associated with the financial performance

of CCS’s construction projects during the Relevant Period. This information was

inconsistent with other reports (such as Overtrade Reports and MPSRs) that

contained much more optimistic assessments of the financial performance of

those projects, as reported to the Board and the Audit Committee.

2.29.
The Board and the Audit Committee were not made aware during the Relevant

Period of the significant and increasing financial risks described above. This meant

they were hampered in providing proper oversight of CCS’s financial performance

and the overly aggressive contract accounting judgements being applied to its

major projects.

2.30.
In light of the above, the Authority considers that, during the Relevant Period,

Carillion failed to take reasonable steps to establish and maintain adequate

procedures, systems and controls to enable it to comply with its obligations under

the Listing Rules, in breach of Listing Principle 1.

2.31.
As the Group CEO with responsibilities for ensuring that Carillion had adequate

procedures, systems and controls, including in relation to financial reporting, and

the Board member with the most expertise on construction and contracting

matters, the Authority considers that during the Relevant Period, Mr Howson was

knowingly concerned in Carillion’s breach of Listing Principle 1.

2.32.
The Authority considers that Mr Howson acted recklessly in relation to the facts

and matters at paragraphs 2.8 to 2.30 above. As a result, Carillion failed to act

with integrity towards its holders and potential holders of its premium listed

shares, in breach of Premium Listing Principle 2, and Mr Howson was knowingly

concerned in Carillion’s breach of Premium Listing Principle 2.

2.33.
The Authority has therefore decided to impose a financial penalty on Mr Howson

in the amount of £397,800 pursuant to sections 91 and 123 of the Act.

3.
DEFINITIONS

3.1.
The definitions below are used in this Notice:

“the Act” means the Financial Services and Markets Act 2000;

“AGM” means Annual General Meeting;

“Announcements” means the December Announcement, the March Results

Announcement and the May Announcement;

“the Authority” means the body corporate known as the Financial Conduct

Authority;

“AWPR” means Aberdeen Western Peripheral Route which was a project structured

as a joint venture with two other partners;

“Battersea” means the Phase 1 Battersea Power Station redevelopment;

“Building” means the Buildings Business Unit within CCS;

“Business Division” means one of the following divisions that Carillion’s business

was divided into during the Relevant Period: CCS, Carillion Services, MENA,

Canada, Al Futtaim Carillion and Carillion Private Finance;

“Business Unit” means a sub-division of CCS, including (amongst others) Building

and Infrastructure;

“Carillion” means Carillion plc;

“CCS” means Carillion Construction Services, a Business Division of Carillion;

“CEO” means Chief Executive Officer;

“December Announcement” means Carillion’s trading update published on 7

December 2016;

“DEPP” means the Decision Procedure and Penalties manual, part of the

Handbook;

“Group” means the Carillion group of companies, of which Carillion plc was the

ultimate parent company;

“Group FD” means the Group Finance Director for Carillion;

“the Handbook” means the Authority’s Handbook of rules and guidance;

“IAS 11” means International Accounting Standard 11;

“Infrastructure” means the Infrastructure & Railways Business Unit within CCS;

“the Listing Rules” means those rules contained in the part of the Handbook

entitled ‘Listing Rules’;

“MAR” means Regulation (EU) No 596/2014 of the European Parliament and of

the Council of 16 April 2014 on market abuse;

“March Results Announcement” means Carillion’s 2016 financial results published

on 1 March 2017;

“May Announcement” means Carillion’s AGM statement published on 3 May 2017;

“MCS” means Major Contracts Summary;

“MENA” means Middle East and North Africa, a Business Division of Carillion;

“MMH” means Midland Metropolitan Hospital;

“MPSR” means Major Project Status Report;

“MCRM” means Major Contracts Review Meeting;

“PBT” means underlying Profit Before Tax;

“Priority Contracts” means these four major projects: AWPR, Battersea, MMH and

RLUH;

“PRM” means Performance Review Meeting;

“Project Team” means the project and commercial managers assigned to

individual major projects;

“RDC” means the Regulatory Decisions Committee of the Authority (see further

under Procedural Matters below);

“Relevant Period” means 1 July 2016 to 10 July 2017;

“RIS” means Regulatory Information Service;

“RLUH” means Royal Liverpool University Hospital;

“the Tribunal” means the Upper Tribunal (Tax and Chancery Chamber); and

“the Warning Notice” means the warning notice given to Mr Howson dated 18

September 2020.

4.
FACTS AND MATTERS

SECTION A: BACKGROUND


4.1.
During the Relevant Period, Carillion was a leading construction, project finance

and support services business operating in the UK, Canada and Middle East. It

was created following a demerger of Tarmac Group in 1999 and subsequent

acquisitions of (amongst others) Mowlem and Alfred McAlpine. Carillion was

admitted to the Official List of the London Stock Exchange.

4.2.
Carillion was a non-trading investment holding company operating through a large

number of subsidiaries and joint ventures. Its internal and external financial

reporting to the market was broadly aligned with its business structure. Carillion’s

business was divided into the following divisions during the Relevant Period: CCS,

Carillion Services, Middle East and North Africa, Canada, Al Futtaim Carillion and

4.3.
Carillion’s construction business was operated by CCS in the UK and by Canada

and MENA respectively for its overseas construction business. Carillion externally

reported its financial results for its UK construction business as part of a business

segment called “Construction Services (excluding the Middle East)”, including

construction activities in CCS and Canada. This segment represented almost 30%

(£1,520.2 million) of Carillion’s revenue for 2016, of which CCS contributed

£1,452.8 million.

4.4.
In the UK, CCS as a Business Division of Carillion was led by Business Divisional

management. CCS was sub-divided into Business Units, including (amongst

others) Building and Infrastructure. Major construction projects reported directly

into these Business Units. Smaller projects reported into Business Units via

regional teams. Each of the Business Units was led by Business Unit management.

Major projects also had their own project and commercial managers.

4.5.
On 10 July 2017, Carillion announced that it was making a provision of £845

million in relation to 58 contracts within its construction business. Of this

provision, £375 million related to CCS and £470 million to overseas markets (the

majority of which related to existing markets in the Middle East and Canada). The

CCS provision was made when Carillion acknowledged that accounting

judgements it had previously made in relation to its construction projects needed

to be revised significantly downwards. The provision included £240 million in

relation to four major UK construction projects: RLUH, Battersea, AWPR and MMH.

SECTION B: MR HOWSON’S ROLES AND RESPONSIBILITIES


4.6.
Mr Howson joined Tarmac in 1995, which became Carillion in 1999. On 1 January

2012, Mr Howson was appointed as Group CEO and remained in post until 10 July

2017. During the Relevant Period, Mr Howson’s responsibilities included:

(1) working closely with the Group FD to ensure Carillion communicated

effectively with investors;

(2) working closely with the Group FD to ensure Carillion had appropriate internal

control processes, including systems and controls to facilitate the appropriate

accounting in compliance with the relevant accounting standards; and

(3) providing effective leadership to Carillion. As one of two executive directors

(the other being the Group FD), he reported to the Board, in particular through

the CEO updates which presented on, amongst other things, the performance

of the construction business, in respect of which he was the Board member

with the most expertise.

SECTION C: IAS 11 AND CONTRACT ACCOUNTING JUDGEMENTS

4.7.
Carillion’s construction business involved operating a large number of construction

projects for different clients in the UK, the Middle East and Canada. These projects

varied widely in terms of their size and complexity. Their financial reporting was

governed by international accounting standards applicable during the Relevant

4.8.
IAS 11 applies a “percentage of completion” methodology to construction

contracts. It provides that, where the final outcome of the contract can be

estimated reliably, revenue and costs are recognised in a financial period by

reference to progress in the contract’s stage of completion. The stage of

completion can be assessed in a variety of ways, including (as was adopted in this

case) by reference to the costs incurred to date as a percentage of the total costs

expected to be incurred on a contract. In simple terms, this means that if 50%

of the expected total costs have been incurred within a financial reporting period,

50% of the costs and revenue associated with the contract should be recognised

in the financial statements for that period. For a profitable contract, the difference

between revenue and costs on the contract represents the margin (e.g. profit)

that can be recognised. For a loss-making contract (i.e. where total costs to the

end of the contract are expected to exceed total revenue), IAS 11 requires that

the total expected loss must be recognised in full immediately.

4.9.
When the outcome of the contract cannot be estimated reliably, revenue can only

be recognised up to the extent of costs incurred that it is probable will be

recovered (i.e. if the outcome of the contract cannot be estimated reliably, no

profit can be recognised), but costs are still recognised in the period they are

incurred.

4.10.
The percentage of completion method therefore typically requires assessment of

the expected revenue and costs up to the end of the contract (commonly referred

to as “end of life”) and the percentage of costs incurred to date. Revenue can

include the initial amount of revenue agreed in the contract, as well as amounts

attributable to “variations” and “claims”. A contract’s profit or loss recognised in

Carillion’s financial reporting up to any particular point in time was called “current

traded margin” or “margin traded to date” by Carillion. The overall profit or loss

that it expected to earn to the end of the contract was known as “end of life

margin”.

4.11.
Variations and claims are a common feature of construction contracts and can

comprise a significant proportion of the revenue recognised in relation to a

contract pursuant to IAS 11. Variations may occur when the scope, timing or

specific requirements of a project are changed by a client. Claims can arise

against a client or a sub-contractor in circumstances where there have been

delays or increased costs in a project due to negligence or some other failure on

the part of the client or sub-contractor. Claims can also be brought by those

parties against the construction company (e.g. Carillion).

4.12.
The application of IAS 11 means that the reporting of a construction contract’s

financial performance is heavily influenced by judgements as to the estimated end

of life revenue and costs of a contract and the likely future recoverability of value

associated with claims and variations. This made the proper application of IAS 11

of fundamental importance to Carillion, ensuring that information it published in

relation to its construction business was not false or misleading and/or did not

contain material omissions (as required by LR 1.3.3R and Article 15 of MAR). It

was also fundamental to Carillion’s obligation pursuant to Listing Principle 1 to

take reasonable steps to establish and maintain adequate procedures, systems

and controls to enable it to comply with its obligations under the Listing Rules.

SECTION D: CARILLION’S PROCEDURES, SYSTEMS AND CONTROLS

4.13.
Carillion’s relevant procedures, systems and controls around contract accounting

judgements within CCS were established prior to the Relevant Period and were

designed around a forecasting process that was supposed to operate on a “bottom

up” basis. In other words, judgements affecting the financial performance of

construction projects were supposed to be led by those most directly involved in

managing the projects, utilising the expertise and experience within the Project

Teams, Business Units and Business Divisions. Their views could, however, be

subject to challenge by more senior management, especially during Carillion’s

budgeting and reforecasting process, and the requirement to report in compliance

with IAS 11 made challenge particularly important in the circumstances.

4.14.
During the Relevant Period, the budget and reforecasting challenges issued and

maintained by senior management (including by Mr Howson) became increasingly

challenging and difficult to achieve as major projects in CCS faced mounting

operational and financial difficulties. These challenges were issued to CCS and

quantified at a Divisional level, as opposed to being referable to individual

projects. They nonetheless put significant pressure on individuals within CCS to

apply increasingly aggressive contract accounting judgements in order to raise

the financial performance of projects to meet what the individuals believed were

unrealistic financial targets. This gave rise to the clear risk that these judgements

would not comply with the requirements of IAS 11 and would misreport the

financial performance of major projects within CCS. Carillion’s procedures,

systems and controls were not sufficiently robust or transparent to address this

risk.

Carillion’s internal policies on revenue and profit recognition

4.15.
The requirements of IAS 11 were reflected in internal policies adopted by Carillion

for financial reporting purposes. Carillion’s profit recognition policy applicable to

CCS construction projects during the Relevant Period provided, amongst other

things, that:

(1)
potentially contentious claims against clients should only be recognised as

revenue where a good draft of the claim had been completed, it was

reasonably certain that the client would agree to the claim and the client

had the ability to pay;

(2)
if not agreed with the client, variations should only be recognised if

supported by a written instruction by the client and an assessment of the

client’s ability to pay; and

(3)
the recognition of any claims or variations must be approved by the Finance

Directors and Commercial Directors of the relevant Business Unit and

Business Division.

4.16.
The above judgements within CCS primarily involved personnel within the

Commercial and Finance functions within Carillion. The role of the Commercial

function was to manage the commercial aspects of projects, including any claims

or variations. The Finance function was responsible for the financial reporting of

projects, including ensuring compliance with applicable accounting standards and

internal policies. Decisions to recognise value associated with claims or variations

required input from both functions to assess recoverability and value, and ensure

that profits were appropriately recognised in Carillion’s accounts.

Application of contract accounting judgements and their reporting within

4.17.
During the Relevant Period, the application of contract accounting judgements

within CCS was dominated by the need to meet the very challenging financial

targets set and maintained by senior management (including Mr Howson). In

practice, this meant that the judgements were no longer made in accordance with

Carillion’s internal policies or on a “bottom up” basis as envisaged in the

forecasting process, but were aligned to meet the targets set and to maintain the

reported profitability of CCS’s major projects. These judgements did not reflect

the true financial position of the projects or the financial risks associated with

them. They did not comply with IAS 11, one of the applicable accounting

standards governing the recognition of revenue and costs associated with

construction contracts.

4.18.
These financial risks and potential exposures arising from these overly aggressive

accounting judgements were highlighted by CCS to Mr Howson and others on a

number of occasions and by various means, including by reporting on:

(1)
“hard risks” associated with CCS’s projects, which were amounts included

within budgeted forecasts, but which were considered by CCS management

as unlikely to be recovered;

(2)
potential exposures to amounts due on major projects by means of a

quarterly report known as the Major Contracts Summary; and

(3)
large and increasing divergences in the financial performance in relation to

certain major projects, making clear the increasingly large disparity for

those projects between the assessments of financial performance by project

and/or management teams within CCS and the financial performance as

reflected in Carillion’s budgeted forecasts.

4.19.
Mr Howson did not respond appropriately to these warning signs. He did not

adjust CCS’s financial targets in response to them. He also did not report them

to the Board or communicate them to the Audit Committee, even though to his

knowledge they were not otherwise being reported or communicated, and even

though he must have been aware, particularly having regard to the nature and

cumulative effect of the warning signs and the number of occasions on which they

were reported to him, that they would be highly relevant to the deliberations of

the Board and the Audit Committee. This meant that the Board and the Audit

Committee were unaware of the full extent of financial risks and potential

exposures within CCS and their significant increase during the Relevant Period.

4.20.
There was no single, coherent process within CCS for making contract accounting

judgements and obtaining approval of them in accordance with Carillion’s policies.

Instead, the financial performance of CCS’s major projects and accounting

judgements associated with them were subject to review and internal reporting

by various processes involving the relevant Project Team, Business Unit

management, Business Divisional management, Mr Howson, Richard Adam

(Carillion’s Group FD during the Relevant Period until 31 December 2016) and

Zafar Khan (Carillion’s Group FD from 1 January 2017, who was previously the

Group Financial Controller), and ultimately the Board and the Audit Committee.

These processes ultimately determined how the financial performance of

individual construction projects was externally reported by Carillion to the market.

Internal reporting on major projects from Project Team up to Mr Howson

(i) Contract Appraisals

4.21.
The Project Teams typically produced monthly Contract Appraisals for each major

project setting out the estimated end of life and current traded value, costs and

margin (“traded” referring to the amounts entered into Carillion’s financial

reports). These figures incorporated the Project Team’s ongoing judgements as

to the potential recoverability of claims or variations, or cost savings, as well as

any additional adjustments applied on top of the Project Team’s judgements

(typically known as “management adjustments” within CCS).

4.22.
These management adjustments applied during the Relevant Period were often

the means by which the financial performance of projects was adjusted upwards

in order to meet budgeted forecasts in line with the targets for CCS set and

maintained by senior management (including Mr Howson). Carillion’s profit

recognition policy specifically prohibited “arbitrary management adjustments” and

indicated that “items must be fully documented and supported at all times”.

However, the policy was not followed in practice. There was no breakdown of the

management adjustments applied to a project identifying the reasons for them

and the specific claims, variations or costs to which they had been applied. Mr

Howson was not himself involved in the making of management adjustments

(because they were made at Business Unit or Divisional level). The practice of

making management adjustments was one of the tools used within CCS, however,

in response to the pressure placed on CCS to meet very challenging financial

targets. This tool was used increasingly during the Relevant Period in order to

maintain the reported profitability of projects, despite the increasing risks. Mr

Howson was aware in January 2017 that by November / December 2016, these

management adjustments amounted to around £245 million within CCS. He was

also aware in April 2017 that they had increased to approximately £310 million

by February / March 2017.

(ii)
Performance Review Meetings

4.23.
The operational, commercial and financial progress of projects within CCS were

considered at Performance Review Meetings. The following PRMs dealing with

major projects took place each month:

(1) a PRM for each individual major project, typically attended by the relevant

Project Team and Business Unit and Divisional management, and sometimes

by Mr Howson;

(2) a Business Unit PRM for each Business Unit, typically attended by Business

Unit and Divisional management;

(3) a Divisional PRM for each Business Division, typically attended by Business

Divisional management and Mr Howson and the Group FD.

4.24.
Discussions at PRMs would include discussion of claims, variations and costs on

different projects, and the challenges or opportunities associated with them,

including their recovery strategy. Despite the potential significance of these

discussions in the context of financial reporting around projects, they were not

minuted and the only record made was a list of agreed actions.

(iii)
Budgeting and reforecasting process

4.25.
The PRMs played an important role in the context of Carillion’s budgeting and

forecasting process. This process involved a budget being produced in October

to December each year, with 3-4 reforecasts (known as RF1, RF2, etc) throughout

the year.

4.26.
As explained above, this process was intended to be “bottom up” and submissions

would be reviewed at Business Unit and Divisional PRMs before being submitted

to the Group finance function and ultimately the Board for approval.

4.27.
The budget and reforecast submissions would be subject to challenge in the form

of revised financial targets, first by management of the relevant Business Division

and subsequently by the Group FD. The pressure to meet challenges imposed and

maintained by senior management (including Mr Howson) required the Project

Teams, Business Units and Business Divisions to work out ways of delivering the

revenue and profitability targets. During the Relevant Period, this was done within

CCS by, amongst other things, using increasingly aggressive judgements as to

the likely recoverability of claims, variations and anticipated cost savings on major

projects, including by means of ever larger management adjustments to maintain

profitability and the use of negative accruals and “audit friendly” Position Papers

(see paragraphs 4.87 and 4.105 below).

(iv) Hard risk

4.28.
The management of CCS and its associated Business Units had significant

concerns about the increasing levels of risk associated with these judgements.

4.29.
CCS categorised risk associated with contract accounting judgements as “hard

risk” or “soft risk”. Hard and soft risks represented attempts to quantify and

report on financial risks associated with CCS’s projects, typically in the context of

Carillion’s budgeting and reforecasting processes. As Mr Howson was aware, hard

risks were amounts included within budgeted forecasts, but which were assessed

by CCS as unlikely to be recoverable. Soft risk was understood within CCS to be

amounts deemed recoverable, albeit there might still be challenges and recovery

was not certain. The reporting of hard risk in PRMs and as part of the budgeting

and reforecasting processes was considered to be especially important by

individuals within CCS in order to highlight internally the risks associated with the

increasingly aggressive contract accounting judgements being applied during the

Relevant Period.

4.30.
As explained below (see paragraphs 4.53 and 4.54), Mr Howson attended CCS

PRMs during the Relevant Period at which the forecast level of hard risk was

highlighted as part of the budgeting and reforecasting process. By October 2016,

hard risk internally reported in the CCS PRM amounted to £172 million. This

increased to £258.4 million by the end of December 2016 and to £310.6 million

by April 2017.

(v)
Major Contracts Summary and Major Contracts Review Meeting

4.31.
The MCS was a quarterly report submitted by the Business Divisions to (amongst

others) Mr Howson during the Relevant Period. It highlighted financial exposures

arising from contentious amounts due on individual major projects, including

claims, flagging the projects with a “red”, “amber” or “green” status. It specifically

highlighted where a likely recovery was less than Carillion’s current forecast,

resulting in an exposure that might need to be written off or could call into

question under IAS 11 the recognition of any revenue, and therefore of any profit,

with respect to those projects. There was, however, no guidance provided to the

Business Divisions for completing the report, which led to a lack of clarity and

consistency in the figures submitted by different Business Divisions. The MCS

nonetheless showed large and increasing exposures across different Business

Divisions (including CCS) during the Relevant Period.

4.32.
In October 2016, the MCS identified a “likely” exposure of £173.2 million within

CCS (up from £159.9 million in July 2016), with 11 out of 16 named projects

marked with a red flag status. By May 2017, this had increased to a “likely”

exposure of over £430 million, with all bar two projects marked with a red flag

status.

4.33.
The MCS was discussed at Major Contracts Review Meetings and circulated in

advance of these meetings. The attendees at the MCRMs would typically include

the Group CEO, the Group FD and management from each Business Division. Mr

Howson received the July and October MCSs by email in advance of MCRMs that

he was due to attend, although it appears he did not subsequently attend those

meetings.

(vi) Peer review

4.34.
Separate to the reporting processes described above, major projects were also

subject to peer reviews which were carried out as part of Carillion’s internal audit

programme. They involved a review of selected projects undertaken by

experienced contract managers from another part of the business. The review

included consideration of the financial position of the relevant project and the

contract accounting judgements applied to it. During the Relevant Period, the

peer review recommendations on certain major projects identified significantly

worse financial performance than the budgeted forecasts. There was, however,

no formal process to ensure that a peer reviewer’s recommendations were taken

into account and no meaningful action taken in response, although as part of

internal
audit
presentations
to
the
Audit
Committee,
peer
review

recommendations were identified as being tracked and implemented.

4.35.
Mr Howson did not receive peer review reports, although he was aware of the

process and indicated which projects he wanted to be peer reviewed.

Reporting to the Board and the Audit Committee

4.36.
Mr Howson was a member of the Board throughout the Relevant Period and

attended the Audit Committee. The Group FD was the only other executive

director who was a member of the Board during the Relevant Period.

4.37.
As Mr Howson knew, the Board and the Audit Committee were responsible for

providing oversight of Carillion’s business and the risks in that business, including

those associated with its financial reporting to the market. The Audit Committee’s

Terms of Reference during the Relevant Period stated, amongst other things, that

the Committee would review and where necessary challenge “whether the

Company has followed appropriate accounting standards and made appropriate

estimates and judgements, taking into account the views of the external auditors”.

4.38.
The internal reporting of hard risks, potential exposures in the MCSs and the large

and increasing divergences from budgeted forecast in the financial performance

of certain major projects represented significant and increasing financial risks

associated with overly aggressive contract accounting judgements being applied

within CCS during the Relevant Period. These risks were known to Mr Howson

during the Relevant Period and he must have been aware, particularly having

regard to the nature and cumulative effect of the information he received

regarding these risks and the number of occasions on which it was reported to

him, that they would be highly relevant to the deliberations of the Board and the

Audit Committee. However, as Mr Howson was aware, these risks were not being

disclosed to the Board or the Audit Committee (through his own reporting or

otherwise). Instead, the Board and the Audit Committee received different

reports that painted a broadly positive picture and failed to highlight the

increasing financial risks arising within CCS during the Relevant Period.

4.39.
The Board received two key reports dealing with (amongst other things) the

financial performance of CCS’s projects: Major Project Status Reports and

Overtrade Reports. Neither report showed the financial risks associated with

increasing management adjustments, hard risks, MCS exposures, divergences

from budgeted forecasts for major projects or variances to peer review

recommendations. Instead, they identified much lower levels of risk associated

with contract accounting judgements and largely maintained the status quo in

terms of the reported financial performance of major projects.

4.40.
MPSRs were quarterly reports on the estimated end of life and current traded

value, costs and margin for individual major projects, with commentary about

progress on each project and major issues and risks. The individual reports were

summarised in a MPSR Executive Summary that identified the value and margin

associated with each major project, together with any changes. Only the MPSR

Executive Summary would be submitted to the Board, after it had been reviewed

and approved by Mr Howson as Group CEO and by the Group FD.

4.41.
Notwithstanding the significantly increasing financial risks within CCS, the figures

in the MPSRs and the MPSR Executive Summary throughout the Relevant Period

were aligned to the latest budget or reforecast figures for each project. This meant

that the MPSRs and the MPSR Executive Summary failed to highlight any

inconsistencies between the latest budget or reforecast and the assessment of the

relevant Project Team, Business Unit or Business Division. Mr Howson received

the information which was inconsistent with the MPSRs. The MPSRs also did not

highlight the management adjustments applied to the projects, amounts identified

as hard risk, exposures in the MCS or variances to peer review recommendations.

4.42.
The Overtrade Report showed the value of construction revenue traded by

Carillion on projects, but not certified by the client. Certification is the formal

acceptance by a client that work has been completed satisfactorily, allowing

payment for it to be made. Revenue traded but not certified represented revenue

that Carillion was recognising in its management accounts for work that was not

yet formally approved by the client. This included revenue recognised in relation

to claims or variations that had not yet been agreed with the client.

4.43.
The Overtrade Report was regarded within Carillion as an important indicator of

the amount of revenue subject to contract accounting judgements that was being

recognised in Carillion’s management accounts at a particular point in time. It

was appended to Carillion’s monthly management accounts circulated to the

Board and separately provided to the Audit Committee.

4.44.
Mr Howson understood the importance of the Overtrade Report. Whilst he

believed “Construction Revenue Traded Not Certified” included both contentious

and non-contentious amounts, he knew the figures reported in the Overtrade

Report did not identify hard risks, exposures reported in the MCS or divergences

from budgeted forecast in the financial performance of certain major projects.

4.45.
The Board did not review contract accounting judgements collectively or on

individual projects as a matter of course. As well as the MPSR Executive Summary

and Overtrade Report, the Board received regular operational updates on major

projects, but these did not typically cover financial performance. Other

management information provided to the Board (such as budgets or monthly

management accounts) included financial information and reflected contract

accounting judgements at an aggregate level only.

4.46.
The Audit Committee received the Overtrade Report, but not the MPSR Executive

Summary. Following the financial period end at half or full year, the Group FD also

submitted a report to the Audit Committee (the meetings of which Mr Howson

attended) identifying the financial risks and key judgements associated with major

projects. This typically identified the forecast end of life margin for each major

project and stated the value that would need to be achieved through claims,

variations or cost savings in order to achieve that margin. It did not, however,

explain the basis of the judgements made or describe the financial risks associated

with them. It did not identify the level of management adjustments being applied,

hard risks, the MCS exposures, divergences from budgeted forecast in the

financial performance of certain major projects or variances to peer review

recommendations. The values identified in the Group FD’s Report were also

different to, and at times inconsistent with, the figures in the Overtrade Report.

Carillion’s financial statements and Position Papers provided to the external
auditors


4.47.
For each financial reporting period, Position Papers on major projects were

prepared by Business Units for the purposes of the external auditors’ half and full

year audit work. They set out the financial position of selected projects in terms

of the estimated end of life and currently traded value, costs and margin. They

identified the amounts being recognised in relation to claims, variations and costs,

but only provided limited narrative or other explanation as to the judgements

being made. They were reviewed at Divisional and Group level as well as provided

to the external auditors. The figures set out in the Position Papers were broadly

equivalent to the MPSRs and reflected the amounts recognised for those projects

in Carillion’s financial statements. The external auditors were therefore not

informed of the internal reporting of hard risks, potential exposures in the MCSs

or the large and increasing divergences from budgeted forecast in the financial

performance of certain major projects.

4.48.
Mr Howson did not receive Position Papers.

SECTION E: EVENTS LEADING UP TO THE ANNOUNCEMENTS

Increase in exposures and risks associated with contract accounting

judgements during the second half of 2016

4.49.
The second half of 2016 saw significant increases in the exposures and levels of

risk associated with Carillion’s contract accounting judgements being reported

internally for CCS and the Group as a whole. For CCS, these increases reflected

significant deteriorations in the financial performance of certain major projects

within CCS as described in Section G below. They were highlighted by CCS to Mr

Howson and others on a number of occasions during the Relevant Period. Mr

Howson must have been aware, particularly having regard to the nature and

cumulative effect of the information he received and the number of occasions on

which these increases were reported to him, that they would be highly relevant

to the deliberations of the Audit Committee, the Board and the external auditors.

However, they were not reported to the Audit Committee, the Board or the

external auditors.

July and October 2016 MCSs

4.50.
In July 2016, the MCS identified a “likely” exposure (ahead of any write-offs) in

relation to contentious amounts considered due (e.g. via claims) to the Group as

a whole of £439.9 million. The equivalent figure for CCS was £159.9 million

(representing 66% of the contentious amounts considered due to CCS). The “best”

case scenario in the MCS anticipated an exposure of just over £136 million for CCS

(i.e. 56% of contentious amounts due).

4.51.
By October 2016, the “likely” exposure in the MCS had increased to £566.6 million

for the Group and to £173.2 million for CCS. The figure for CCS represented 71%

of the contentious amounts considered due. The “best” case scenario in the MCS

was an exposure of just under £142 million for CCS (i.e. 58% of contentious

amounts due).

4.52.
Mr Howson received the MCSs for July and October 2016. He did not, however,

take any steps to address these increasing exposures being reported to him.

Hard risk reported in August and October 2016 and January 2017

4.53.
In August 2016, CCS’s RF3 flash presentation forecast hard risk for the end of

2016 of £172.7 million, including £61.8 million of new hard risk since January

2016. This was an increase of new hard risk of £36.1 million from RF2 in April

2016. This presentation was emailed to Mr Howson on 11 August 2016 and he

dialled into part of the PRM at which the presentation was discussed.

4.54.
In October 2016, CCS’s Profit Update Year End & Budget forecast a similar level

of hard risk of £171.8 million for 2016, with £149.6 million of hard risk forecast

by the end of 2017. Mr Howson attended the relevant PRM.

4.55.
In January 2017, CCS was reporting in its PRM that hard risk had increased to

£258.4 million by the end of December 2016. Mr Howson attended this PRM.

4.56.
As a result, the hard risk forecast reported by CCS increased by £61.8 million

between January and August 2016 and by a further £85.7 million between August

and December 2016. As explained above, hard risk represented amounts viewed

by CCS as unlikely to be recovered. Mr Howson must have understood this to be

the case given his accumulated knowledge and experience, together with an email

sent to him on 18 March 2016 that specifically characterised hard risk as “not

collectible” (sic). However, Mr Howson took no meaningful steps to understand,

assess or address the increasing levels and accumulated values of hard risk being

reported to him.

Lack of proper reporting to the Board and the Audit Committee about increasing

financial risks and exposures

4.57.
As Mr Howson knew, the significant increases in likely MCS exposures and high

levels of hard risk during the second half of 2016 were not highlighted to the

Board or the Audit Committee. The Board was regularly updated during this period

as to operational developments on major projects, but not their financial impact

or the accounting judgements made on individual contracts.

4.58.
The financial information available to the Board and the Audit Committee about

these matters at CCS level during the Relevant Period was contained in Overtrade

Reports. The Overtrade Reports issued to the Board and the Audit Committee

between July and December 2016 showed no significant increase in risk for the

Group or CCS. In addition, the Overtrade Reports did not provide the Board or

the Audit Committee with information about what those within CCS considered

were likely exposures – instead the reports showed revenue “traded not certified”

(i.e. amounts that had not yet been agreed with the client which were reported

as being appropriate to recognise as revenue). In these Reports, construction

revenue traded but not certified was consistently reported at around £295 million

for the Group, as was the equivalent figure for CCS at around £42 to £44 million.

These figures do not reconcile with or convey the much higher likely exposures

and hard risks described above. No steps were taken by Mr Howson to address

these matters, despite the fact that Overtrade Reports were appended to the

MCSs and the discrepancy in the reporting of these risks would have been readily

apparent to him (as he received the July and October 2016 MCSs, unlike the Board

and the Audit Committee).

4.59.
In August 2016, a member of the Audit Committee queried whether contract

accounting judgements being made and their linkage to the financial statements

could
be
made
clearer
because
“trying
to
assess
the
judgemental

risks/opportunities is difficult”. It was noted that this would be reviewed going

forward, but no substantive changes were made during 2016 or 2017 to the level

of information being provided to the Audit Committee.

No increase in provisions

4.60.
The level of provisions against risks associated with major projects was reported

to the Board each month as part of the monthly management accounts. Total

provisions for the Group reviewed by the Board were consistently maintained at

£27.1 million throughout 2016, with other provisions and contingencies increasing

this to £50.1 million in total by the 2016 year-end. The amount of provisions and

contingencies allocated to CCS remained broadly at £16.9 million. There was no

material increase in the size of the provisions or contingency to address the

increasing exposures identified in the MCS and the high levels of hard risk

reported by CCS.

4.61.
As a member of the Board, Mr Howson was aware of the provisions seen by the

Board during the Relevant Period. Despite this, he did not take steps to address

the discrepancy between (i) the level of Group provisions and (ii) the increasing

exposures identified in the MCS and the high levels of hard risk internally reported

by CCS of which he was aware.

The December Announcement

4.62.
The market consensus for Carillion’s underlying profit before tax was around £180

million for the 2016 full year. In early December 2016, Carillion was considering

how to meet this expectation and was exploring possible one-off transactions or

introducing more “stretch” for CCS in order to bridge a perceived Group PBT

shortfall of £33 million against market expectations. In the end, the gap was

bridged for the Group in part by means of a one-off transaction with an

outsourcing supplier, which delivered an additional £20 million of profit for 2016.

This enabled the Group FD, Mr Adam, to report to the Board “The positive news

that our overall expectations for Group profit and earnings are broadly in line with

our expectations enabled us to keep the consensus forecasts for total underlying

profit and earnings broadly unchanged.” Mr Howson attended the Board meeting

at which this was reported.

4.63.
The trading performance of the Group was discussed at a Board meeting on 6

December 2016, including risks to Carillion’s year-end profit forecast. Board

members emphasised their reliance upon the “judgment of the executive” in

relation to certain major projects, including AWPR, as well as the need to

“understand whether trading performance of the business had deteriorated”. Mr

Howson did not take this opportunity to relay to the Board information about the

increasing exposures in the MCSs or the high levels of hard risk within CCS.

4.64.
Carillion published its Full Year Trading Update (i.e. the December Announcement)

on 7 December 2016. The December Announcement was headed ‘Meeting

expectations led by a strong performance in support services”. It referred to

“expected strong growth in total revenue and increased operating profit”. For

Construction Services (excluding the Middle East), Carillion reported that “We

expect a solid revenue performance in this segment, with the operating margin

remaining within our target range of 2.5 per cent and 3.0 per cent. This result

once again reflects our selective approach to choosing the contracts for which we

bid in order to focus on maintaining a healthy operating margin”. In terms of

outlook, the December Announcement stated that Carillion was “well positioned

to make further progress in 2017”. The announcement did not mention or reflect

the increasing financial risk being reported within CCS. Carillion’s share price fell

3% on the announcement.

4.65.
Mr Howson was closely involved in the process for preparing and reviewing the

December Announcement. At the Board meeting on 6 December 2016, he

approved the December Announcement as a member of Carillion’s Board.

The March Results Announcement

4.66.
At the Board meeting on 26 January 2017, concerns were expressed about lack

of clarity over the Group’s trading performance towards the end of 2016 and the

need for transparency and clarity “particularly if the position had deteriorated in

the year”. It was noted, however, that trading for the last two months of 2016

was in line with forecast. This was broadly consistent with the MPSR Executive

Summary for January 2017, which showed no material deterioration in the

financial performance of CCS’s major projects since the previous quarter.

4.67.
However, it was not consistent with the MCS in February 2017. This showed a

likely exposure of £528.4 million (ahead of any write-offs) for the Group and of

£149.2 million for CCS. These exposures excluded any figures for two of the

largest contracts within CCS (AWPR and RLUH).

4.68.
Whilst the Authority has not seen any evidence that Mr Howson reviewed the

February MCS, at around this time Infrastructure was estimating a loss for AWPR

equivalent to an exposure of £68 million against its traded margin (-£10 million),

and RLUH’s Project Team was estimating a likely loss of £56.3 million (which

equated to an exposure of almost £68 million against its traded margin). Mr

Howson received both of these forecasts. The inclusion of these figures in the

MCSs would have increased the likely exposure to £664.4 million for the Group

and to £285.2 million for CCS. This was an increase in exposures since December

2016 of £45.7 million for the Group and of £59.4 million for CCS.

4.69.
Final Position Papers for selected contracts were submitted to the external

auditors on 11 January 2017. The margin recorded in these Position Papers was

broadly consistent with the MPSRs prepared for January 2017. The Position Papers

did not disclose the increase in hard risk since August 2016, the likely exposures

identified against some of these projects in MCSs between July and December

2016, the scale of management adjustments being applied to them, the

deterioration in the Project Teams’ and Infrastructure’s assessment of their

financial performance, or variances to peer review recommendations. Mr Howson

did not receive these Position Papers, but he was aware of the figures in the MPSRs

which were consistent with the margin recorded in the Position Papers (see

paragraph 4.47 above).

4.70.
On 23 February 2017, the Audit Committee met to review the draft 2016 Annual

Report and Accounts. The Group FD’s Year-End Report for this meeting referred

to construction revenue traded not certified of £294 million for the Group and of

£44 million for CCS, as set out in an appended Overtrade Report. It also identified

the key judgements made in relation to certain major projects across the Group

(including within CCS) and the claim recoveries and costs savings necessary in

order to meet the margins traded for these contracts in Carillion’s accounts. The

Year-End Report asserted that a total provision of £17 million was appropriate at

the year-end for the Construction Services segment (including CCS and Canada).

This, when combined with other provisions and contingencies, gave a year-end

provision for CCS of £16.9 million. Mr Howson attended this meeting.

4.71.
The Year-End Report did not comment upon the merits of the claims, the likelihood

of successfully achieving the recoveries or cost savings, or the Project Teams’ and

Infrastructure’s assessment of deteriorating financial performance in certain

major projects. It did not identify the large financial risks associated with them,

for example, as reflected in hard risks, the exposures identified in the MCS, the

level of management adjustments being applied and variances to peer review

recommendations. It was also inconsistent with the appended Overtrade Report

with regard to AWPR, insofar as AWPR had a nil value cited in the Overtrade

Report compared to a claim of £30 million against the client referenced in the

Group FD’s Report.

4.72.
During the meeting, an Audit Committee member commented that the projects

were complex and it was difficult to second-guess management judgements. This

emphasised the importance of ensuring that those judgements were appropriately

made and disclosed to the Audit Committee. In the meeting, the Group FD, Mr

Khan, acknowledged there was not a consistent practice between Business

Divisions for completing the Overtrade Report and that a new methodology for

reporting uncertified balances would be adopted.

4.73.
The 2016 Annual Report and the March Results Announcement were reviewed by

the Audit Committee at its meeting on 23 February 2017, approved at the Board

meeting on 28 February 2017 and published on 1 March 2017. Mr Howson

reviewed and approved the Annual Report and the March Results Announcement

as a Board member. There were no material changes in this announcement to the

30

expectations that had been communicated to the market in the December

Announcement.

4.74.
The March Results Announcement was headed ‘Performance in line with

expectations’. It referred to revenue of £4,394.9 million for the Group (an

increase of 11% from 2015), with PBT of £178 million (a 1% increase from 2015).

4.75.
The attached document published with the March Results Announcement stated

for “Construction services (excluding the Middle East)” that “Revenue grew

strongly by 21 per cent to £1,520.2 million (2015: £1,258.3 million), driven by

growth in the UK where revenue increased to around £1.5 billion (2015: £1.2

billion), reflecting a number of high-quality contract wins for both infrastructure

and building over the last 18 months”. It went on to state that “Underlying

operating profit increased to £41.3 million (2015: £37.8 million) with an operating

margin of 2.7 per cent (2015: 3.0 per cent), which remains within our target

range of 2.5 per cent to 3.0 per cent”. It described the ambition for 2017 in this

business segment was “to maintain revenue and profit broadly at their current

levels”.

4.76.
The Chairman’s statement in the March Results Announcement stated that

Carillion had a “good platform from which to develop the business in 2017. We

will accelerate the rebalancing of our business into markets and sectors where we

can win high-quality contracts and achieve our targets for margin and cash flows,

while actively managing the positions we have in challenging markets”. The

statement about “challenging markets” was a reference to markets in the Middle

East and Canada. There was, however, no reference to challenges in UK

construction contracts.

4.77.
Market analyst reports following the March Results Announcement broadly noted

that the results were in-line with expectations, with a focus on debts and the

performance of contracts in support services, the Middle East and Canada.

Following the announcement, Carillion’s share price fell by 5%.

SECTION F: RECOGNITION OF THE NEED FOR A PROVISION

Events following publication of the 2016 year-end results

4.78.
By March 2017, the hard risk for CCS had increased to £310.6 million. This was

an increase of £137.9 million since the level of CCS hard risk was forecast in

August 2016 and £52.2 million since hard risk was reported at the CCS PRM on

18 January 2017. Mr Howson was aware of the March 2017 hard risk figure of

£310.6 million through his attendance at the CCS PRM meeting in April 2017, at

which it was reported.

4.79.
During April and early May 2017, the position continued to worsen. An MCS dated

4 May 2017 showed a likely exposure against contentious amounts due of £872.3

million for the Group and £431.9 million for CCS (representing 71% of the

contentious amounts due to CCS). This was an increase to the likely exposure of

£207.9 million for the Group and of £146.7 million for CCS since February 2017.

Mr Howson was sent this MCS on 5 May 2017.

4.80.
In April 2017, Mr Howson attended a CCS PRM which highlighted further

deteriorations in CCS contracts, notably RLUH, MMH and Battersea. These are

described in more detail in Section G below.

4.81.
A significant change in Carillion’s debt position was reported to and discussed at

a Board meeting on 3 May 2017. Mr Howson attended this meeting. Concerns

were raised by Board members during the course of that discussion that trading

was “going backwards”, a “significant number of major contracts were

deteriorating” and there were “too many problem contracts”.

4.82.
Later that same day, Carillion issued its AGM Statement (the May Announcement)

under the headings “Trading conditions unchanged” and “Positive work winning

performance”. Mr Howson was closely involved in drafting the May Announcement

and approved it as a Board member. It stated that Mr Howson would make the

following comments at that day’s AGM:

"Trading conditions across the Group's markets have remained largely unchanged

since we announced our 2016 full-year results in March. Consequently, we

continue to focus on the priorities we set out when we announced our 2016

results, namely to accelerate the rebalancing of our business into markets and

sectors where we can achieve our objectives for margins and cash flows; and to

manage challenging contract positions, particularly in our international markets,

as these are key to achieving our objective of reducing average net borrowing.”

4.83.
The reference to “challenging contract positions” was aimed at highlighting the

deterioration in the financial performance of Carillion’s contracts. As with the

March Results Announcement, however, the statement was explicitly linked to

Carillion’s overseas markets, not the UK, and so gave the misleading impression

that trading conditions in the UK market had not deteriorated.

4.84.
Following the announcement there was some market commentary relating to

challenging contracts in the Middle East, and the share price fell by 5%.

Negative accruals

4.85.
During April and May 2017, additional concerns were raised within CCS that “the

level of risk which is being held in the balance sheet appears too large relative to

the size of the business”. These concerns were prompted by the discovery of the

use of negative accruals within CCS, a practice that was generally prohibited in

Carillion’s accounting policies.

4.86.
Negative accruals (as prohibited by Carillion) describes the practice of using the

value of claims to reduce costs accounted for on a project, instead of recognising

the claim as revenue. The practice can be neutral from an accounting perspective

because the profitability of a project should remain the same, whether the claim

is recognised as a reduction to cost or an increase to revenue. Within Carillion,

however, accounting judgements around claims were reported and assessed

internally and to external auditors in the context of revenue recognition, not costs.

This enabled negative accruals to be used on certain major projects within CCS to

reduce costs by means of overly aggressive judgements on claim recoveries

without disclosing that fact in Position Papers seen by the external auditors. For

example, a claim for £8 million might have been recognised at the 2016 year-

end, of which £5 million was recognised as revenue and £3 million as a negative

accrual that reduced costs. The external auditors would only see a value of £5

million for the claim (i.e. the part recognised as revenue), not the additional £3

million recognised by means of the negative accrual. In this way, the profitability

on these projects could be maintained without subjecting the overly aggressive

accounting judgements being used to appropriate scrutiny.

4.87.
An email sent by an individual within CCS in April 2017 explained the use of

negative accruals as follows:

“Our profit targets have mean [sic] that we have not been able to write these

back to their correct positions. In order to get through audit with a justifiable

route-map we have had to suppress costs. This has, unfortunately been done by

applying negative accruals. Generally any overtrading we do push through is via

revenue adjustments rather than through costs but in these cases we couldn’t

produce a position paper that would get through audit. We asked the sites to

produce a “clean” version of the position paper so that we had full visibility of the

adjustments that were being made.”

4.88.
An internal Carillion investigation into the use of negative accruals was

commenced in April 2017, at which point Mr Howson was informed. The

investigation reported its initial findings to Mr Howson on 7 May 2017 (four days

after the May Announcement). It identified that the majority of negative accruals

related to four major contracts (including RLUH, Battersea and AWPR) and

amounted to a total of £102 million. It also identified that Business Units had

used negative accruals on certain contracts in CCS in response to pressure to

“hold the position [i.e. profit margin]”. This was a reference to the pressure to

meet financial targets imposed on CCS described at paragraph 4.14 above.

4.89.
On 9 May 2017, the Board was informed about the use of negative accruals and

a Board sub-committee was set up to oversee the internal investigation into their

use. The sub-committee did not include Mr Howson, but he (together with the

Board and the Audit Committee) was regularly updated as to the progress of the

investigation.

4.90.
As part of the internal investigation, the negative accruals were reversed so that

the full value of claims recognised at the 2016 year-end could be properly

assessed in order to determine whether or not a prior year adjustment was

required. The effect of reversing the negative accruals significantly increased the

reported costs of the projects and required much more value from claims to be

recognised as revenue in order to justify their originally reported year-end margin.

Using the above example of a claim for £8 million, the effect of reversing the

negative accrual meant that Carillion had to justify recognising the full £8 million

of the claim as revenue, not £5 million as originally disclosed internally and to the

external auditors. In its investigation, Carillion sought to justify the 2016 year-

end position by significantly increasing the value of certain claims and in some

cases introducing new claims or revenue streams that were said to have been in

management’s mind as at the year-end (albeit not recorded in the original Position

Papers in December 2016).

4.91.
Following the conclusion of this investigation, the Board concluded on 23 May

2017 that the value, costs and margin recognised at the 2016 year-end for each

contract could be justified following the investigation and there was therefore no

need to restate the 2016 year-end accounts. A lessons learnt report subsequently

submitted to the Board noted that “Management need to be aware that high-level

instructions such as that to “hold the position” (i.e. maintain the traded margin)

may, if crudely implemented, have unintended consequences.”

Enhanced Contracts Review

4.92.
By late May / early June 2017, Carillion recognised that the deterioration in the

financial performance of its projects and increasing debt position meant it needed

to raise additional capital. It explored the possibility of a rights issue. As part of

any rights issue, Carillion was advised that it should de-risk its balance sheet.

This essentially meant reviewing the values of assets on its balance sheet,

including any values recognised in its accounts associated with variations or

claims on construction projects across the Group, and writing off any values

deemed to be at risk of non-recovery. This became known as the “Enhanced

Contracts Review”.

4.93.
The Enhanced Contracts Review took place over June and early July 2017. It

involved a review of 58 projects representing £1.58 billion of receivables and 47%

of Group revenue for the period ending 31 May 2017. The review considered all

aspects of the projects, including the judgements made on each project in relation

to variations or claims included in estimated end of life forecasts.

4.94.
The review was conducted with assistance from the external auditors, who do not

appear to have been provided with details of hard risks, MCS exposures or peer

reviews. It concluded that the traded value of a number of projects in Carillion’s

construction business exceeded the commercial assessment of those positions. It

identified a possible exposure of between £378 million and £693 million, and

recommended a provision of £695 million. Given the magnitude of the proposed

impairment, the external auditors asked Carillion to consider whether any of the

proposed provisions required a prior year adjustment to its 2016 results.

Carillion’s management (not including Mr Howson) considered 11 major contract

positions to assess whether there was evidence that should have been obtained

and considered in preparing the Group’s 2016 year-end results ahead of their

publication on 1 March 2017. Carillion produced a paper assessing the issues that

gave rise to the provision on these projects and considered whether those issues

were known as at 31 December 2016. It concluded that the challenges on these

projects had crystallised after publication of the results and no prior year

adjustment was required.

4.95.
The recommended provision of £695 million was reported to the Audit Committee

at its meeting on 9 July 2017, which Mr Howson attended. The provision across

CCS projects was £375 million. Even with a provision at that level, certain projects

retained values being traded that were identified as being at risk. The decision

was therefore taken to increase the provision to £845 million to address those

risks, which was later allocated to specific projects in September 2017. No prior

year adjustment was made.

Trading update on 10 July 2017

4.96.
On 9 July 2017, the Board approved the Audit Committee’s recommendation. On

10 July 2017, Carillion announced the contract provision of £845 million as part

of a trading update, with £375 million being attributed to the UK and £470 million

attributed to overseas markets. It stated that the majority of the overseas

provision related to exiting markets in the Middle East and Canada.

4.97.
Carillion’s share price fell 39% that day, and within three days had fallen by a

4.98.
In the provision announced by Carillion on 10 July 2017, the four largest

provisions within CCS were as follows:

(1)
RLUH: £68 million.

(2)
Battersea: £38 million.

(3)
AWPR: £86 million.

(4)
MMH: £48 million.

4.99.
It was announced that Mr Howson had stepped down as CEO on 10 July 2017.

SECTION G: THE LARGEST WRITE-DOWNS ON UK MAJOR CONTRACTS

RLUH

4.100. RLUH was a project to construct a new Private Finance Initiative hospital located

on the existing Royal Liverpool University Hospital site. It started in February 2014

and was originally forecast to be completed in March 2017. The project was

operated by the Buildings Business Unit within CCS.

4.101. The tender value of the project was £286 million, with an estimated end of life

profit margin of £10.2 million (or 3.56%).

36

4.102. Despite significant delays in the project in 2015 and 2016, Carillion had increased

the end of life margin forecast associated with this project to £13.6 million (or

4.6%) by July 2016. The increased margin was maintained by the use of

management adjustments, increasing from £38.9 million in July 2016 to almost

£72 million by February 2017. During most of the Relevant Period, the Board and

the Audit Committee were not aware of the scale of management adjustments

and the divergence between the internal reporting within CCS and what was being

reported to them in relation to RLUH’s financial performance.

4.103. There were significant and increasing divergences between (on the one hand) the

Project Team’s views on RLUH’s financial position and the financial risks reported

by CCS to Mr Howson and others; and (on the other hand) those reflected in

budgeted forecasts and/or reported to the Board and the Audit Committee during

the Relevant Period. These are illustrated in the following graph:

Graph 1 - Each point on the graph shows the end of life (EOL) margin and/or traded to date margin
recorded in various reports pertaining to RLUH as variously reported to Building, CCS, the executive
directors, the Board, the Audit Committee and/or the external auditors. The orange and blue trend
lines illustrate the increasing divergence of views across the year between the position as assessed
by the Project Team and/or in peer reviews (blue line); and the view post-management
adjustments reflecting budgeted forecasts and/or reported to the Board, the Audit Committee and
the external auditors (orange line). The graph also shows the level of hard risk reported in hard
risk schedules and the “likely” exposure to traded amount reported in the Major Contract
Summaries. The red circles show the figures of which Richard Howson was aware at that point in
time (or subsequently in the case of MPSRs), whether that was by way of being present in meetings
or receiving information directly by email.

4.104. This divergence between the internal reporting within CCS and the reporting to

the Board and the Audit Committee in the second half of 2016 is summarised

The Project Team’s assessments

(1)
The Contract Appraisals and other commercial reports prepared by the

Project Team from July to December 2016 reported a deteriorating end of

life margin loss for RLUH and the increasing use of management

adjustments to achieve the forecast profit margin of 4.9%. These Appraisals

and reports were not seen by Mr Howson. He was, however, made aware

of the Project Team’s views by other means.

(2)
In September 2016, the Project Team sent a spreadsheet by email to Mr

Howson and certain Business Unit and Divisional management summarising

what it saw as the realistic end of life position for RLUH. This identified a

“clean end out forecast position” of a £50 million loss on the project, with

“realistic” recovery targets potentially reducing this to a £14 million loss and

other potential benefits further reducing it to an £8 million loss.

(3)
The Project Team’s end of life margin forecast for RLUH was reported by

CCS as a £21 million loss in a “profitability workshop” in September 2016.

The same figure was highlighted in a CCS PRM in October 2016. Mr Howson

attended both of these meetings.

(4)
By November 2016, the Contract Appraisal was reporting an end of life

forecast loss of £38.9 million (or -12.6%) before any management

adjustments. This assessment was confirmed by a peer review in November

2016, which noted the use of management adjustments to maintain the

profit margin and described this as “extremely ambitious and would mean

full success with all claims identified”. The Authority has not seen any

evidence that Mr Howson was aware of this Contract Appraisal or peer

review during the Relevant Period.

CCS’s reporting to Mr Howson

(5)
CCS reported the Project Team’s views internally as described above. At

the profitability workshop in September 2016 attended by Mr Howson, CCS

reported that for RLUH a 4.7% margin (equivalent to an £11.3 million profit)

38

had been traded to date (i.e. recognised in Carillion’s financial reporting)

compared to the £21 million loss assessed by the Project Team. The

presentation indicated that the Project Team had been challenged to achieve

“breakeven” (i.e. no profit or loss).

(6)
At the CCS PRM in October 2016 attended by Mr Howson, the margin traded

for RLUH to date was reported by CCS as being £12.2 million compared to

the Project Team’s assessment of a £21 million loss (a difference of £33.2

million). The presentation highlighted hard risk of £10 million against RLUH,

having previously been assessed at £3 million in April 2016 and £7 million

in August 2016. Shortly after the year-end, this was further increased to

£23 million.

(7)
The July 2016 MCS reported a “likely” exposure to traded amount of £10

million for RLUH and assigned a “Red” flag status to the project. In the

October 2016 MCS, this had increased to £21 million with a “Red” status.

This represented 100% (i.e. the full amount) of the contentious amounts

identified as due in these MCSs. Mr Howson received the July and October

Reporting to the Board and the Audit Committee

(8) The MPSR Executive Summaries, Overtrade Reports, CEO and Group FD’s

reports to the Board and/ or the Audit Committee did not reflect the Project

Team’s assessments or peer review recommendation as to the financial

performance of RLUH. They also did not highlight the financial risks associated

with RLUH, including the level of management adjustments being applied or

the hard risks and MCS exposures internally reported by CCS. To that extent,

they omitted highly material and relevant information concerning RLUH’s

financial performance during the Relevant Period. Instead, the MPSR

Executive Summaries maintained an end of life forecast profit of £13.6 million

in July and October 2016 and of £13.2 million in January 2017 for RLUH and

the Overtrade Reports identified £6 million or £8 million only as revenue

traded not certified.

4.105. Mr Howson was in receipt of the MCS for July and October 2016 and the monthly

Overtrade Reports submitted to the Board and/or the Audit Committee. He was

therefore aware of the divergence between the forecast profits and limited

financial risks for RLUH being reported to the Board and the Audit Committee by

these means compared to what was being reported by the Project Teams and CCS

as described above. He failed to bring this divergence to the attention, or

otherwise take steps to ensure it was brought to the attention, of the Board or

the Audit Committee.

4.106. Ahead of the 2016 year-end, two versions of the RLUH Position Paper were

produced by Building: a “clean” version reflecting the Project Team’s assessment

of a £38.7 million loss (-12.6% margin) and an “audit friendly” version

incorporating adjustments of £53 million to meet the forecast end of life profit of

£14 million (4.44% margin). The “audit friendly” version was used for the purpose

of the audit of Carillion’s 2016 Annual Report and Accounts as announced on 1

March 2017; the external auditors were not provided with the “clean” version of

the Position Papers. The Authority has not seen any evidence that Mr Howson was

aware of the preparation of these different versions. The need to produce them

at all emphasises the overly aggressive nature of the accounting judgements

being used in response to pressure to achieve the targets set and maintained by

senior management (including Mr Howson).

4.107. The final version of the Position Paper submitted to the external auditors for the

2016 year-end accounts showed a slightly reduced end of life margin of £13.2

million (or 4.42%), with costs of £286.1 million. It recognised £25.4 million as

revenue to be recovered from claims (excluding any additional claim amounts

recognised by means of negative accruals). As at the end of December 2016, all

of these claims (which were not subject to formal legal proceedings at that stage)

were disputed or no response had been received. Their progress was not sufficient

to be deemed as “reasonably certain” (as per Carillion’s internal policies) or

“probable” (as per IAS 11) to be recovered. No revenue should have been

recognised in relation to them.

4.108. At the CCS PRM on 18 January 2017, the Business Unit reported the Project

Team’s estimated loss of £39 million (-13%) as at November 2016, with a

management adjustment of £53.9 million applied to help achieve a traded to date

margin of 4.7% (£11.7 million). Mr Howson attended this PRM.

4.109. On 8 February 2017, the Project Team sent a briefing on RLUH to Mr Howson and

certain Business Unit and Divisional management. It was sent ahead of a RLUH

presentation at a CCS PRM on 10 February 2017, which Mr Howson attended. This

included a financial analysis reporting a “realistic” estimated loss of £56.3 million

for RLUH as at 2 February 2017, with a “best case” loss of £43 million and “worst

case” loss of £76.1 million.

4.110. This information was not communicated to the Board or the Audit Committee by

Mr Howson or, to his knowledge, by anyone else. The RLUH MPSR for January

2017 was consistent with the final Position Paper submitted to the external

auditors in reporting an estimated end of life margin of 4.4% (or profit of £13.2

million). The Group FD’s Report submitted to the Audit Committee meeting on

23 February 2017 referred to the need to achieve £25.5 million recoveries in

relation to claims to achieve the forecast end of life margin of 4.44%. In their

Audit Memorandum presented to the meeting, the external auditors noted that

“management [remain] confident of full recovery [on RLUH] due to the number

of routes available”. No reference was made to the Project Team’s assessments

of a significant loss, the scale of management adjustments being applied, hard

risks or MCS exposures, about which the Audit Committee and the external

auditors remained unaware.

4.111. On 1 March 2017, Carillion announced its 2016 financial results in its March

Results Announcement. The cost, value and margin recognised for RLUH as part

of the figures released in this announcement reflected the final Position Paper

provided to the external auditors in January 2017, with costs of £286.1 million

and a forecast end of life margin of 4.42% (i.e. a profit of £13.2 million). The

recognition of these amounts meant that the revenue and profit / margin figures

for the Group and Construction Services (excluding the Middle East) in the March

Results Announcement were materially misstated due to an understatement of

costs and the recognition of claims as revenue in non-compliance with Carillion’s

internal policies and IAS 11.

4.112. The financial performance of RLUH as reported internally continued to deteriorate

after March 2017. The Project Team’s forecast of a £49 million loss (-16.4%) as

at January 2017 was reported in the CCS PRM in March 2017, with a management

adjustment of £61.5 million being applied to help achieve a traded to date margin

of £11.7 million (4.6%). The CCS PRM in April 2017 reported that the Project

Team was estimating a loss of almost £60 million on RLUH as at February 2017,

with a management adjustment of almost £65 million being applied to help

support a traded to date margin of £11.7 million (4.5%). These traded to date

margins were equivalent to an end of life margin of over £13 million. Mr Howson

attended both of these PRMs. Mr Howson did not report these divergences, or

otherwise take steps to ensure they were reported, to the Board or to the Audit

Committee.

4.113. The MCS in May 2017 identified a likely exposure of £71.5 million for RLUH. A

copy of this MCS was sent to Mr Howson by email on 5 May 2017. The size of this

exposure was reflected in CCS’s reporting at a PRM attended by Mr Howson on 19

May 2017, which referred to the Project Team estimating a loss of £59.3 million,

with a management adjustment of £67 million to help support a traded to date

profit of £11.7 million as at March 2017.

4.114. On 7 June 2017, the Board held a strategy meeting. At this meeting, Mr Howson

presented an “Overview of Key Contract Positions across the Group”. In the

presentation, RLUH was reported as having a forecast end of life margin of £11.7

million (3%). This was expressly stated as including claims in the forecast traded

at 100% (i.e. the entirety of the claim values was recognised in the forecast). At

the CCS PRM on 22 June 2017 attended by Mr Howson, the Project Team’s

estimated loss was reported as being £62.6 million, with a management

adjustment of £74 million to help achieve a traded to date profit figure of £11.7

million as at April 2017.

4.115. Following the Enhanced Contracts Review, £68 million was provided against RLUH.

This amount formed part of the contract provision of £845 million announced by

Carillion on 10 July 2017.

4.116. Battersea was a project to design and build a mixed-use development including

866 apartments, leisure facilities and retail units. The contract was signed on 27

December 2013 with an original contract completion date in September 2016.

4.117. The contract was tendered at a value of £443.7 million with a 0% profit margin.

4.118. Carillion encountered a number of issues with the Battersea contract in 2015 and

2016, which caused significant delays to the project. These issues in large part

arose from pressure caused by the client issuing a large volume of variations to

the work and the late provision of key utilities to the work site.

4.119. By January 2016, there had been a contract reset on Battersea which increased

the contract value to £472.4 million and extended the contract completion date

4.120. In July 2016, Carillion reported a positive end of life margin of £10.7 million

(2.2%) in the MPSR Executive Summary for Battersea. This increase in value was

partially attributed to a claim of £11.5 million for a further reset (“Reset 2”). By

contrast, the Project Team estimated a forecast end of life loss of £24.7 million (-

5%) in July 2016. This gap continued to increase during the Relevant Period and

was bridged by means of large management adjustments, rising from a

management adjustment of £28.6 million in July 2016 to around £34 million in

December 2016. The Board and the Audit Committee were unaware of the scale

of the management adjustments and the divergence between the internal

reporting within CCS and what was being reported to them in relation to

Battersea’s financial performance.

4.121. There were significant and increasing divergences between (on the one hand) the

Project Team’s views on Battersea’s financial position and the financial risks

reported by CCS to Mr Howson and others; and (on the other hand) those

reflecting budgeted forecasts and/or reported to the Board and the Audit

Committee during the Relevant Period. These are illustrated in the following

Graph 2 - Each point on the graph shows the end of life (EOL) margin and/or traded to date margin
recorded in various reports pertaining to Battersea Power Station as variously reported to Building,
CCS, the executive directors, the Board, the Audit Committee and/or the external auditors. The

orange and blue trend lines illustrate the increasing divergence of views between the position as
assessed by the Project Team and/or in peer reviews (blue line); and the view reflected in budgeted
forecasts and/or reported to the Board, the Audit Committee and the external auditors (orange line).
The graph also shows the level of hard risk reported in hard risk schedules and the “likely” exposure
to traded amount reported in the Major Contract Summaries. The red circles show the figures of
which Richard Howson was aware at that point in time (or subsequently in the case of MPSRs),
whether that was by way of being present in meetings or receiving information directly by email.

4.122. This divergence between the internal reporting within CCS and the reporting to

the Board and the Audit Committee in the second half of 2016 can be summarised

as follows:

The Project Team’s assessments

(1)
The Contract Appraisals prepared by the Project Team from July to

December 2016 reported a deteriorating end of life margin loss for

Battersea. Increasing levels of management adjustments were applied to

the current traded value and costs to maintain a positive current traded

margin of just over 2% (a current traded profit margin of £8 million and

equating to an end of life profit of around £10 million). By December 2016,

the Project Team’s forecast in the Contract Appraisal had worsened to a

forecast end of life loss of £30 million, with end of life costs of £534.7 million

and a management adjustment of just under £34 million to maintain the

current traded margin of £8 million (or 1.8%). In October 2016, a peer

review report on Battersea recommended recognising an end of life loss of

£28 million.

(2)
The Contract Appraisals and peer review report were not seen by Mr

Howson, but he was aware of the Project Team’s assessments by alternative

means. In September 2016, the Project Team’s end of life margin forecast

for Battersea was reported by CCS as a £25 million loss in a “profitability

workshop” in September 2016. An estimated £14.8 million loss was

highlighted in a CCS PRM in October 2016. Mr Howson attended both of

these meetings.

CCS’s reporting to Mr Howson

(3)
CCS reported the Project Team’s views internally as described above. At

the profitability workshop in September 2016, CCS reported that Battersea

had a traded margin of 2.1% to date (equivalent to just over £8 million)

compared to the Project Team’s projected end of life loss of £25 million, and

that the Project Team had been challenged to achieve “breakeven” (i.e. no

profit or loss).

(4)
At the CCS PRM in October 2016, CCS reported the margin traded to date

on Battersea as being £8 million compared to the Project Team’s assessment

of a £14.8 million loss (a difference of £22.8 million). The presentation also

highlighted hard risk of £13 million against Battersea, the same as

previously internally reported for that project.

(5)
The July and October 2016 MCSs reported a “likely” exposure of £21 million

for Battersea and assigned a “Red” flag status to the project. This exposure

represented 53% of the contentious amounts of £39.9 million identified in

the MCSs as due on Battersea. Mr Howson received these MCSs.

Reporting to the Board and the Audit Committee

(6)
The MPSR Executive Summaries, Overtrade Reports, CEO and Group FD’s

reports presented to the Board and the Audit Committee did not reflect the

Project Team’s views or peer review recommendation as to Battersea’s

financial performance. They also did not highlight the financial risks

associated with Battersea, including the level of management adjustments

being applied or the hard risks and MCS exposures reported by CCS. To

that extent, they omitted highly material and relevant information

concerning Battersea’s financial performance during the Relevant Period.

(7)
Instead, during the Relevant Period the MPSR Executive Summaries showed

only a minor deterioration in end of life margin from £10.7 million (or 2.2%)

in July 2016 to £10.1 million (or 2%) in October 2016 and £8.6 million (or

1.7%) in January 2017. The Overtrade Reports similarly only identified a

small increase in revenue traded not certified, from £4 million in July 2016

to £6 million in December 2016.

(8)
Mr Howson was in receipt of the MPSR Executive Summaries for July and

October 2016 and January 2017 and the monthly Overtrade Reports

submitted to the Board and/or the Audit Committee. He was therefore

aware of the divergence between the forecast profits and limited financial

risks for Battersea being reported to the Board and the Audit Committee by

these means compared to what was being reported by the Project Teams

and CCS as described above. He did not, however, raise these matters, or

otherwise take steps to ensure these matters were raised, with the Board

or with the Audit Committee.

4.123. At the 2016 year-end, two sets of figures were produced when drafting Position

Papers for the external auditors, including for Battersea. The “clean” Position

Paper reported a loss of £25.6 million; the “audit friendly” version incorporated

adjustments to maintain a positive end of life margin of £8 million, a difference of

£33.6 million. The “audit friendly” version was used for the purpose of preparing

Carillion’s 2016 Annual Report and Accounts as announced on 1 March 2017. The

Authority has not seen any evidence that Mr Howson was aware of the preparation

of these different versions. The need to produce them at all emphasises the overly

aggressive nature of the accounting judgements being used in response to

pressure to achieve the targets set and maintained by senior management

(including Mr Howson).

4.124. At the January CCS PRM on 18 January 2017, the Business Unit reported the

Project Team’s estimated loss of £26.3 million (-5.2%) as at November 2016, with

a management adjustment of £31.2 million to help achieve a traded to date

margin of £8 million (or 1.9%). Mr Howson attended this PRM.

4.125. The Group FD’s Report submitted to the Audit Committee meeting on 23 February

2017 referred to the need to achieve £28.6 million recoveries in relation to claims,

which they expected to deliver through a contract reset to achieve the forecast

end of life margin of 2.0% (equivalent to £10.1 million). In their Audit

Memorandum presented to the meeting, the external auditors noted that “Carillion

no longer need to achieve £19.3 million in future cost savings, instead

management is targeting an additional £28.6 million recovery from the client

through a second reset.” No reference was made to the Project Team’s

assessment of a significant loss, the scale of management adjustments being

applied, hard risks or MCS exposures, about which the Audit Committee and the

external auditors remained unaware.

4.126. On 1 March 2017, Carillion announced its 2016 financial results in its March

Results Announcement. The cost, value and margin recognised for Battersea as

part of the figures released in this announcement reflected the final Position Paper

provided to the external auditors in January 2017, with a forecast end of life

margin of 1.5% (i.e. a profit of just over £8 million). The recognition of these

amounts meant that the revenue and profit / margin figures for the Group and

Construction Services (excluding the Middle East) in the March Results

Announcement were materially misstated due to the inclusion of £28.6 million

associated with the contract reset in revenue and the understatement of costs,

which should have more closely reflected the Project team’s view of £534.7 million

as opposed to the figure of £516.4 million traded in Carillion’s accounts. This

overstatement of revenue and understatement of costs was not in compliance

with Carillion’s internal policies or IAS 11.

4.127. At the CCS PRMs in March and April 2017 (showing January and February 2017

figures), the Project Team reported an increased estimated loss of £34.8 million

for Battersea. Management adjustments of over £39 million were applied to help

bring the end of life margin back to a traded to date margin of £8 million (1.7%).

This was equivalent to an end of life margin of around £8.5 million. Mr Howson

attended both of these PRMs.

4.128. The MCS in May 2017 identified a likely exposure of £33 million for Battersea. A

copy of this MCS was sent to Mr Howson by email on 5 May 2017.

4.129. At the CCS PRM in May 2017 attended by Mr Howson, the Project Team’s reported

estimates had worsened to a forecast loss of £36.6 million, with a £41.5 million

management adjustment being applied to support a traded profit to date of £8

million as at March 2017.

4.130. On 7 June 2017, the Board held a strategy meeting. At this meeting, Mr Howson

presented an “Overview of Key Contract Positions across the Group”. In the

presentation, Battersea was reported as having a forecast end of life margin of £8

million (1.5%). This was expressly stated as including claims in the forecast

traded at 100% (i.e. the entirety of the claim values was recognised in the

forecast). At the CCS PRM on 22 June 2017 attended by Mr Howson, the Project

Team was estimating a £47.8 million loss, with a management adjustment of

£42.7 million required to support a traded to date figure of £8 million as at April

2017.

4.131. Following the Enhanced Contract Review, £38 million was provided in relation to

Battersea. This amount formed part of the contract provision of £845 million

announced by Carillion on 10 July 2017.

4.132. MMH was a project to construct a new Private Finance Initiative hospital in the

West Midlands. The contract started on 11 December 2015, with an original

completion date of 20 July 2018.

4.133. The contract was tendered at a value of £296.7 million at a 5.97% margin (or

£17.7 million).

4.134. The period between Carillion bidding for MMH and financial close on 11 December

2015 was the shortest in Carillion’s history.

4.135. The progress of MMH was disrupted at an early stage by two main issues:

(1) Problems with the design and procurement processes arising from a short bid

period; and



(2) Adverse weather, with heavy rainfall flooding parts of the building under

construction, impacting on productivity.

4.136. As of July 2016, MMH was nine weeks behind the target construction programme

as a result of the issues referenced above.

4.137. Despite the delay to the progress of MMH, Carillion was reporting in the MPSR

Executive Summary for July 2016 that MMH had an estimated end of life margin

of 6%, equating to £17.9 million. This forecast was not supported by the Project

Team, who in the July 2016 Contract Appraisal for MMH reported a deterioration

in the end of life margin to 3.8% (£11.3 million). Notwithstanding this, the end of

life margin of £17.9 million was maintained by use of a management adjustment

of £6.6 million.

4.138. From November 2016, there were significant and increasing divergences between

(on the one hand) the Project Team’s views on MMH’s financial position and the

financial risks reported by CCS to Mr Howson and others; and (on the other hand)

those reflecting budgeted forecasts and/or reported to the Board and the Audit

Committee. This is illustrated in the following graph:

Graph 3 - Each point on the graph shows the end of life (EOL) margin and/or traded to date margin
recorded in various reports pertaining to MMH as variously reported to Building, CCS, the executive
directors, the Board, the Audit Committee and/or the external auditors. The orange and blue trend
lines illustrate the increasing divergence of views across the year between the position as assessed
by the Project Team and/or in peer reviews (blue line); and the view reflected in budgeted forecasts
and/or reported to the Board, the Audit Committee and the external auditors (orange line). The
graph also shows the level of hard risk reported in hard risk schedules and the “likely” exposure to
traded amount reported in the Major Contract Summaries. The red circles show the figures of which
Mr Howson was aware at that point in time (or subsequently in the case of MPSRs), whether that
was by way of being present in meetings or receiving information directly by email.

4.139. This divergence between the internal reporting within CCS and the reporting to

the Board and the Audit Committee during the latter part of 2016 is summarised

below. There is no evidence that Mr Howson was aware of the facts and matters

referenced at sub-paragraphs (1) and (2) below, but they are set out to provide

context to the financial performance of MMH in 2017.

(1) The Contract Appraisals from October to December 2016 reported a

deteriorating end of life margin for MMH, culminating in a forecast of an end

of life margin loss of £2.8 million (-0.9%) and a current traded margin loss of

£0.8 million (-0.9%) in December 2016. These margins reflected increasing

costs from £283 million to £304.8 million. Increasing levels of management

adjustment were applied, principally to the current traded figures during this

period to maintain a current traded margin of 6% to 6.6% (approximately

£6.5 million).

(2) A peer review report dated 8 November 2016 recommended an end of life

margin of £nil and that no further margin should be traded on MMH until

detailed designs had been provided and procurement issues had been

substantially advanced.

(3) The MPSR Executive Summaries to the Board and/or the Audit Committee for

July and October 2016 did not reflect the Project Team’s assessments.

Instead, they consistently maintained an end of life forecast profit of around

£17.9 million (6%) for MMH, as Mr Howson was aware.

4.140. The final version of the Position Paper for MMH submitted to the external auditors

for the 2016 year-end accounts reported costs of £284 million, revenue of £302

million and forecast an end of life margin of £18.1 million. The true costs were,

however, closer to £304.8 million as reported by the Project Team (i.e. almost

£21 million more than reported in the Position Paper). This meant that the profit

recognised on MMH at the 2016 year-end was not in accordance with IAS 11 and

was materially misstated. Mr Howson did not see this Position Paper.

4.141. The January 2017 MPSR was broadly consistent with the Position Paper and

referred to an end of life profit margin for MMH of 6%, which amounted to £17.7

million. By contrast, the Commercial Report for the CCS PRM in January 2017

identified MMH as amongst the top five projects within Building with the biggest

deterioration in end of life margin. It reported that MMH’s end of life margin had

deteriorated from 6% in December 2015 to 4.8% in October 2016 to 1% in

November 2016. Mr Howson attended this PRM.

4.142. The Contract Appraisal for January 2017 incorporated a “Margin Improvement

Plan” that provided for £15.5 million of claim recoveries. This had the effect of

taking the end of life forecast margin to £6.2 million (2%). This was not consistent

with the deterioration reported at the January CCS PRM above. The Contract

Appraisal in February 2017 reversed these changes and showed a forecast end of

life loss of £15.7 million (-5.2%), with a management adjustment of £12.9 million

applied to help maintain a forecast profit margin of just under £18 million.

4.143. On 1 March 2017, Carillion announced its 2016 financial results in its March

Results Announcement. The cost, value and margin recognised for MMH as part

of the figures released in this announcement reflected the final Position Paper

provided to the external auditors in January 2017, with costs of £284 million and

a forecast end of life margin of 6% (assessed as a profit of just over £18 million).

This was a material misstatement of MMH’s financial position due to the level of

costs recognised, which should have more closely reflected the Project Team’s

estimate of £304.8 million. The understatement of costs was not in compliance

with Carillion’s internal policies or IAS 11. The Authority has not seen any

evidence that Mr Howson was aware of this understatement as at 1 March 2017.

4.144. The internal reporting about the financial performance of MMH continued to

diverge in the second quarter of 2017. By April 2017, a Peer Review report stated

that MMH was 10 weeks behind schedule and recommended that the traded

margin should be a loss of £26.7 million, including recommended end of life costs

of £330 million. By the end of April 2017, the Project Team reported an estimated

end of life loss of £32.1 million (-10.6%). The forecast end of life costs had risen

at this stage to £334 million. A management adjustment of almost £20 million

was applied to the current traded margin for MMH to take it from a loss of £11.2

million (-10.6%) to a profit of £8.8 million (6.1%).

4.145. In April 2017, Mr Howson attended a CCS PRM at which it was reported that the

Project Team was forecasting a £15.7 million loss as at February 2017, with a

management adjustment of £12.9 million applied to help maintain a traded to

date profit margin of £7.8 million (consistent with an end of life margin of over

£17.7 million).

4.146. MMH first appeared on the hard risk schedule in April 2017 as a new and emerging

risk of £24 million. It also appeared for the first time in the MCS in May 2017. It

was recorded with a “likely” exposure to traded amount of £32 million and a “Red”

flag status was applied. A copy of this MCS was sent to Mr Howson by email on 5

May 2017.

4.147. At the CCS PRM in May 2017, it was reported that the Project Team was estimating

a loss of £21 million, with a management adjustment of £15.7 million being

applied to support a traded profit to date of £8.4 million as at March 2017. Mr

Howson attended this PRM.

4.148. On 7 June 2017, the Board held a strategy meeting. At this meeting, Mr Howson

presented an “Overview of Key Contract Positions across the Group”. In the

presentation, MMH was reported as having a forecast end of life margin of £25.2

million (7%). This was expressly stated as including claims in the forecast traded

at 100% (i.e. the entirety of the claim values was recognised in the forecast). At

the CCS PRM on 22 June 2017 attended by Mr Howson, the Project Team was

estimating a £32.1 million loss and a management adjustment of £20 million to

support a traded to date figure of £8.8 million as at April 2017.

4.149. Following the Enhanced Contracts Review, MMH was written down by £48 million.

This amount formed part of the contract provision of £845 million announced by

Carillion on 10 July 2017.

AWPR

4.150. AWPR was a design build finance operate contract2 for the construction of a 58km

ring road around Aberdeen. It was structured as a joint venture with two other

partners. The project started in January 2015. Within Carillion, it was managed

by the Infrastructure Business Unit of CCS.

4.151. The tender value for AWPR was £533 million, including costs of around £496

million and a 7% profit margin of £37 million. Carillion’s one-third share was

£177.8 million, with a margin of £12.4 million.

4.152. During 2015 and 2016, AWPR was significantly delayed by poor weather and

delays in diverting statutory utilities (such as water pipes, electricity cables, etc).

4.153. By July 2016, Infrastructure was reporting estimated end of life costs of £679

million and a final margin loss of £52 million at joint venture level, after taking

into account estimated recoveries on claims for delays in diverting the statutory

utilities and insurance claims for delays caused by bad weather. Despite this,

however, an end of life profit margin of £12.4 million (7%) was reported in the

July 2016 MPSR Executive Summary.

4.154. By October 2016, Carillion had reduced the forecast end of life margin for AWPR

to a loss of £10 million. Despite this downwards revision, there were significant

and increasing divergences during the Relevant Period between (on the one hand)

Infrastructure’s views on AWPR’s financial position as reported to Mr Howson and

others; and (on the other hand) those reflecting budgeted forecasts and/or

reported to the Board and the Audit Committee. These are illustrated in the

following graph:


2 DBFO is a project delivery structure in which a private sector party is awarded a contract to design, construct,
finance and operate a capital project. In consideration for performing its obligations under the agreement, the
private sector party may be paid by the government agency.

Graph 4 - Each point on the graph shows the end of life (EOL) margin and/or traded to date margin
recorded in various reports pertaining to AWPR as variously reported to Infrastructure, CCS, the
executive directors, the Board, the Audit Committee and/or the external auditors. The orange and
blue trend lines illustrate the increasing divergence of views between the position as assessed by
the joint venture Project Team and Infrastructure (blue line); and the view reflecting budgeted
forecasts and/or reported to the Board, the Audit Committee and the external auditors (orange line).
The graph also shows the level of hard risk reported by the site teams in the hard risk schedules
and the “likely” exposure to traded amount reported in the Major Contract Summaries. The red
circles show the figures of which Mr Howson was aware at that point in time (or subsequently in the
case of MPSRs), whether that was by way of being present in meetings or receiving information
directly by email.

4.155. This divergence between the internal reporting by Infrastructure and CCS to Mr

Howson and the reporting to the Board and the Audit Committee during the

second half is 2016 is summarised as follows:

Infrastructure and CCS reporting to Mr Howson

(1) In September 2016, CCS reported in a “profitability workshop” that there was

a potential end of life loss of £30 million on AWPR. This was compared in the

presentation (seen by Mr Howson) to a £10 million loss forecast within RF4 at

around that date.

(2) In October 2016, CCS reported at the CCS PRM Profit Update Year End &

Budget that AWPR was being traded at a £10 million loss and there was no

margin or write off forecasted in the budget. The same presentation stated

that hard risk for AWPR amounted to £20 million. Mr Howson attended this

(3) In the MCSs for July and October 2016, AWPR was identified as having a

“likely” exposure of £13.1 million, with a “Red” flag status. This represented

44% of the total contentious amount of £30 million identified in these MCSs

as due on the project. Mr Howson received these MCSs.

(4) On 19 November 2016, an internal Carillion email to (amongst others) Mr

Howson addressed the cash position on AWPR and referred to an “estimated

end of life loss of £40 million our share (after recovery) or £120 million at a

100% JV level”.

(5) On 16 December 2016, Infrastructure gave a presentation to the CCS PRM

with an estimated “most likely” end of life margin loss for Carillion of £78

million on AWPR, with end of life costs estimated by the joint venture Project

Team at £900 million (joint venture level) (Carillion share £300 million). Mr

Howson attended this PRM.

Reporting to the Board and the Audit Committee

(6) The MPSR Executive Summaries, Overtrade Reports, CEO and Group FD’s

reports to the Board and/or the Audit Committee during the Relevant Period

did not reflect the above matters. As noted above, the profit margin for AWPR

in the October 2016 MPSR was revised downwards to a £10 million loss and

this was subsequently maintained in the January 2017 MPSR Executive

Summary. The Overtrade Report showed AWPR as having no revenue traded

not certified (i.e. it suggested that there was no client revenue recognised in

Carillion’s management accounts that was “at risk”). This was incorrect

because Infrastructure was relying upon claims of over £33 million even to

achieve its forecast £78 million loss for AWPR. It was also inconsistent with

the two Group FD’s Reports in the Relevant Period which referred to AWPR

relying on claims.

(7) On 9 November 2016, the Board was informed of “an unexpected increase in

the end out cost of the contract. The extent of the increase is not yet fully

understood and further work is being undertaken to evaluate, control and,

where possible, reduce/mitigate these costs”. AWPR was also discussed at a

Board meeting on 6 December 2016 as one of the potential risks to achieving

Carillion’s year-end profit forecast of £178 million. It was noted in the minutes

that the Board was reliant on the judgement of the executives around AWPR

as well as another project.

(8) Whilst concerns around AWPR were raised with the Board, the end of life

estimates being reported by Infrastructure, hard risks and likely MCS

exposures (of which Mr Howson was aware) were not reported to the Board

or the Audit Committee. Mr Howson was aware of the disparity between these

matters and what was reported in the MPSR Executive Summaries for July and

October 2016 and the monthly Overtrade Reports submitted to the Board

and/or the Audit Committee. Despite this, he did not take steps to draw these

matters to their attention.

4.156. The Position Paper for AWPR at the 2016 year-end reflected the position as

reported in the October 2016 MPSR Executive Summary, with end of life costs

estimated at £652.6 million at joint venture level (Carillion’s cost being £217.5

million) and a margin loss of £30 million (Carillion’s share being a £10 million

loss).

4.157. In November 2016, concerns were expressed by one member of the Infrastructure

management team that he felt “compromised” by the position adopted in the

Position Paper and that there were “some real credibility challenges going

forward.” These concerns were not communicated to the Board, the Audit

Committee or the external auditors.

4.158. The Position Paper submitted to the external auditors for the 2016 year-end

accounts recognised £30 million as revenue to be recovered from claims

(excluding any additional claim amounts recognised by means of negative

accruals). This included a claim for which £23.3 million of revenue was recognised

(“Claim 1”). As at the end of December 2016, the progress of Claim 1 was not

sufficient to be deemed “reasonably certain” (as per Carillion’s internal policies)

or “probable” (as per IAS 11) to be recovered. No revenue should have been

recognised in relation to it.

4.159. Infrastructure’s estimate of a £78 million loss on AWPR was repeated in a further

presentation given at the CCS PRM in January 2017 (attended by Mr Howson).

Shortly afterwards, the hard risk for AWPR was increased to £66 million; Mr

Howson became aware of this in April 2017. Despite this, the January 2017 MPSR

was unchanged and continued to report an estimated end of life loss for AWPR of

£10 million.

4.160. The Group FD’s Report submitted to the Audit Committee meeting on 23 February

2017 referred to the need to achieve £30 million recoveries in relation to claims

and £25 million of costs savings to achieve a revised forecast end of life margin

of -2.8%, which was a loss of £10 million as recognised in the 2016 Annual

Accounts. In its Audit Memorandum presented to the meeting, the external

auditors noted that, in order to achieve the £10 million loss, £55 million of value

needed to be obtained which included claims and costs savings. No reference was

made to the Project Team’s assessment of a significant loss, the scale of

management adjustments being applied, hard risks or MCS exposures, about

which the Audit Committee and the external auditors remained unaware.

4.161. On 21 February 2017, a member of the Audit Committee emailed Mr Khan, the

Group FD, (copying Mr Howson among others) to specifically question him on

various points concerning AWPR ahead of the Audit Committee meeting on 23

February 2017. Despite being aware by this time that Infrastructure considered

that the “most likely” forecast for AWPR was a loss of £78 million and that, even

on the “best case” scenario, the forecast remained a loss of £49 million, neither

Mr Khan nor Mr Howson informed the Audit Committee member of any of the

matters raised in the CCS PRM presentations, including the forecast losses which

far outstripped the figure reported to the Audit Committee. Mr Khan’s email

response to the Audit Committee member on 22 February 2017, which Mr Howson

was copied into, instead described the position on AWPR as “somewhat fluid”.

4.162. On 1 March 2017, Carillion announced its 2016 financial results in its March

Results Announcement. The cost, value and margin recognised for AWPR as part

of the figures released in this announcement reflected the final Position Paper

provided to the external auditors, with a forecast end of life margin loss of £10

million and costs of £217.5 million. The recognition of these amounts meant that

the revenue and profit / margin figures for the Group and Construction Services

(excluding the Middle East) in the March Results Announcement were materially

misstated due to an understatement of costs and the recognition of Claim 1 as

revenue in non-compliance with Carillion’s internal policies and IAS 11.

4.163. By April 2017, the estimated end of life costs had risen to £925 million (including

cost reductions), with a forecast end of life margin loss of £308.3 million (£95.7

million Carillion share). This was reported at the CCS PRM that month attended

by Mr Howson, along with traded loss of £10 million and a hard risk figure of £66

million for AWPR. The estimated loss of £95.7 million (compared to a traded loss

of £10 million) was reported again at the CCS PRMs in May and June 2017

attended by Mr Howson, as was the hard risk figure of £66 million for AWPR.

4.164. The MCS in May 2017 identified a likely exposure of £85 million for AWPR, with a

“red” flag status. However, the MPSR Executive Summary appended to it

indicated that Carillion was continuing to a forecast margin loss of £10 million

only. A copy of this MCS was sent to Mr Howson by email on 5 May 2017.

4.165. On 7 June 2017, the Board held a strategy meeting. At this meeting, Mr Howson

presented an “Overview of Key Contract Positions across the Group”. In the

presentation, AWPR was reported as having a forecast end of life margin of a loss

of £10 million, with over £121 million of value to be recovered from claims. This

was expressly stated as including claims in the forecast traded at 80% (i.e. the

majority of the claim values were recognised in the forecast).

4.166. Following the Enhanced Contracts Review, AWPR was written down by £86 million.

This amount formed part of the contract provision of £845 million announced by

Carillion on 10 July 2017.

5.
FAILINGS

5.1.
In light of the facts and matters above, Mr Howson was:

(1) in respect of all three of the Announcements, knowingly concerned in

Carillion’s dissemination of information that gave false or misleading signals

as to the value of its shares in circumstances where it ought to have known

that the information was false or misleading (in breach of Article 15 of MAR);

(2) in respect of all three of the Announcements, knowingly concerned in

Carillion’s failure to take reasonable care to ensure that its announcements

were not misleading, false or deceptive and did not omit anything likely to

affect the import of the information (in breach of LR 1.3.3R);

(3) knowingly concerned in Carillion’s failure to take reasonable steps to establish

and maintain adequate procedures, systems and controls to enable it to

comply with its obligations under the Listing Rules (in breach of Listing

Principle 1); and

(4) knowingly concerned in Carillion’s failure to act with integrity towards the

holders and potential holders of its premium listed securities (in breach of

Premium Listing Principle 2).

5.2.
These breaches are set out below and the provisions referred to are set out at

Annex A to this Notice.

Carillion’s obligations

5.3.
Article 15 of MAR states that a person shall not engage in or attempt to engage

in market manipulation.

5.4.
Article 12(1)(c) of MAR provides that market manipulation comprises

disseminating information through the media, including the internet, or by any

other means, which gives, or is likely to give, false or misleading signals as to

(amongst other things) the price of a financial instrument, where the person who

made the dissemination knew, or ought to have known, that the information was

false or misleading.

5.5.
Article 12(4) of MAR states that “Where the person referred to in this Article is a

legal person, this Article shall also apply, in accordance with national law, to the

natural persons who participate in the decision to carry out activities for the

account of the legal person concerned”.

5.6.
The “national law” for the purpose of Article 12(4) can be found in section 131AD

of the Act, which provides that “An individual participates in a decision by a body

corporate for the purposes of… Article 12(4) (market manipulation)… where: (a)

the individual was an officer of the body corporate when the decision was made;

and (2) the [Authority is] satisfied that the individual was knowingly concerned in

the decision.”

The December Announcement

5.7.
Mr Howson in his capacity as CEO was an officer of Carillion at the time of the

December Announcement. As one of its two executive directors he had an

important role in preparing and finalising the December Announcement, including

reviewing its content, providing comments on it and approving it as a member of

Carillion’s Board.

5.8.
The December Announcement referred to Carillion’s performance “meeting

expectations”, with expectations for “strong growth in total revenue and increased

operating profit” for the Group and “operating margin” for CCS remaining within

a target range of 2.5-3% for the 2016 year-end. It described Carillion as “well

positioned to make further progress in 2017”.

5.9.
These positive statements were not justified and were made notwithstanding that

at the Board meeting, which took place on the day before the December

Announcement, there had been discussions around a possible deterioration in the

trading performance of the business and the 2017 Budget had been described as

“challenging”. They did not reflect the true financial performance of CCS’s

construction contracts and the announcement omitted any reference to the

significant financial risks associated with these stated expectations. This is

despite the fact that, as at 7 December 2016, Carillion and Mr Howson were aware

that the following issues had been identified and reported within Carillion:

(1)
The MCS prepared for the quarterly meeting on 3 October 2016, which was

sent to Mr Howson by email on that date, identified a likely financial

exposure of £566.6 million for the Group and £173.2 million for CCS. Even

taking into account any inconsistencies in the production of this report, these

figures highlighted very significant likely exposures on major contracts,

including within CCS.

(2)
As part of its 2016 RF3 and 2017 Budget submissions, CCS had reported to

Mr Howson (and others) that hard risk was forecast to amount to £171.8

million by the end of 2016 and £149.6 million by the end of 2017

respectively. These were amounts that were not likely to be recovered, a

significant proportion of which should have been written off in accordance

with IAS 11.

(3)
In the period prior to release of the December Announcement, the expected

financial performance of certain major contracts was much worse than the

budget
and
reforecasts
providing
the
basis
for
the
December

Announcement. Mr Howson was aware of the following facts in this regard:

a. For RLUH, the Project Team had internally reported an expected loss of

between £14 million and £21 million, not the profit of £13.6 million

forecast in the July and October 2016 MPSRs. A likely financial exposure

of £21 million for RLUH in the October 2016 MCS and hard risk of £10

million had been internally reported by CCS.

b. For Battersea, the Project Team had internally reported an expected

loss of between £14 million and £25 million, compared to the forecast

profit of around £10 million in the July and October 2016 MPSRs. A

likely financial exposure of £21 million in the October 2016 MCS and

hard risk of £13 million had been internally reported by CCS.

c. For AWPR, the Board (including Mr Howson) had been informed on 9

November 2016 about an “unexpected increase in the end out cost of

the contract”. At the Board meeting on 6 December 2016 (attended by

Mr Howson), AWPR was identified and discussed as one of the potential

risks to the profit forecast for the 2016 year-end. In the period between

these two Board meetings, Mr Howson (and others) had received an

email referring to an “estimated end of life loss of £40m”. This

compared to a forecast loss of £10 million in the October 2016 MPSR.

The hard risk for AWPR had been internally reported at £20 million.

5.10.
The Authority considers that Mr Howson and Carillion ought to have known that

the information in the December Announcement was false or misleading by reason

of the above matters. The Authority attributes the knowledge of Mr Howson, and

another person, to Carillion for its finding in this regard.

5.11.
By disseminating false or misleading information in circumstances where it ought

to have known the information was false or misleading, Carillion committed

market manipulation in breach of Article 15 of MAR. In the circumstances, and

by virtue of his knowledge and involvement in the December Announcement, Mr

Howson was knowingly concerned in Carillion’s breach of Article 15.

5.12.
The Authority considers that Mr Howson was aware that there was a risk that the

December Announcement was false or misleading due to the matters at

paragraphs 5.7 to 5.9 above. He did not respond appropriately to this risk and

failed to take it properly into account when reviewing and approving the December

Announcement. He also failed to inform the Board and the Audit Committee about

these matters for the purpose of their review and approval of the December

Announcement. This is despite the fact that he must have been aware,

particularly having regard to the nature and cumulative effect of the information

he received from CCS management highlighting increasing levels of financial risks

and exposures associated with the financial performance of CCS’s construction

contracts and the number of occasions on which such information was reported

to him, that these matters would be highly relevant to their deliberations. The

Authority considers that Mr Howson acted recklessly as a result.

The March Results Announcement

5.13.
The March Results Announcement reported on Carillion’s financial results for the

year ended 31 December 2016.

5.14.
Mr Howson in his capacity as CEO was an officer of Carillion at the time of the

March Results Announcement. As one of its two executive directors, he had an

important role in preparing and finalising the announcement, including reviewing

its content, providing comments on it and approving it as a member of Carillion’s

Board.

5.15.
The March Results Announcement and the document published alongside it

described Carillion’s performance as “in line with expectations”, with increased

revenue of £4,394.9 million and PBT of £178 million for the Group and revenue

of £1,520.2 million and operating profit of £41.3 million for “Construction Services

(excluding the Middle East)”. It described strong revenue growth in this segment

and confirmed that operating margin profit for this segment “remains in our target

range of 2.5 per cent to 3 per cent”. It referred to its ambition “to maintain

revenue and profit at broadly their current levels” in 2017. It went on to refer to

Carillion as a whole having a “good platform from which to develop the business

in 2017”. These statements were consistent with the expectations set out in the

December Announcement.

5.16.
The revenue and profit / margin figures for the Group and Construction Services

(excluding the Middle East) in the March Results Announcement were misstated

because they did not accurately reflect the financial performance of the Priority

Contracts. In particular, Carillion failed to recognise the costs and revenue

associated with these projects in accordance with IAS 11. The revenue and profit

/ margin figures were materially overstated as a result. This also made false or

misleading the references to Carillion’s performance being “in line with

expectations”, with strong revenue growth and operating profit targets being met

for the business segment including CCS. While it referred to “actively managing

the positions we have in challenging markets”, this statement was specifically

made in relation to markets in the Middle East and Canada and in the context of

rebalancing Carillion’s business. There was no reference to challenges in the UK

market or to the deteriorating financial performance of CCS’s construction

projects.

5.17.
The positive statements in the March Results Announcement about expected

performance in 2017 were similar to those contained in the December

Announcement. These statements were not justified by the facts and matters

known to Carillion (and Mr Howson) as at the date of the announcement on 1

March 2017. In addition to the matters identified at paragraph 5.9 above, far

from improving since December 2016 the financial performance of Carillion’s

construction contracts had continued to deteriorate. Within CCS (and to the

knowledge of Mr Howson and another person) it was being reported that:

(1)
hard risk had increased to £258.4 million by the end of December 2016;

(2)
for RLUH, the Project Team had internally reported a likely end of life loss

of £56.3 million against a forecast profit margin of 4.4% (i.e. a profit of £13

million);

(3)
for Battersea, the Project Team was estimating an end of life loss of £26.3

million against a forecast profit margin of around 2% (i.e. a profit of around

£8 million); and

(4)
for AWPR, Infrastructure had internally reported a likely end of life loss of

£78 million against a forecast loss of £10 million.

5.18.
The above matters made the positive statements and revenue and profit / margin

figures in the March Results Announcement false or misleading.

5.19.
The Authority considers that Mr Howson and Carillion ought to have known that

the information in the March Results Announcement was false or misleading by

reason of the above matters. The Authority attributes the knowledge of Mr

Howson and another person to Carillion for its finding in this regard.

5.20.
By disseminating false or misleading information in circumstances where it ought

to have known the information was false or misleading, Carillion committed

market manipulation in breach of Article 15 of MAR. In the circumstances, and

by virtue of his knowledge and involvement in the March Results Announcement,

Mr Howson was knowingly concerned in Carillion’s breach of Article 15.

5.21.
The Authority considers that Mr Howson was aware that there was a risk that the

March Results Announcement was false or misleading due to the matters at

paragraphs 5.14 to 5.17 above. He did not respond appropriately to this risk and

failed to take it properly into account when reviewing and approving the March

Results Announcement. He also failed to inform the Board and the Audit

Committee about these matters for the purpose of their review and approval of

the March Results Announcement. This is despite the fact that he must have been

aware, particularly having regard to the nature and cumulative effect of the

information he received from CCS management highlighting increasing levels of

financial risks and exposures associated with the financial performance of CCS’s

construction contracts and the number of occasions on which such information

was reported to him, that these matters would be highly relevant to their

deliberations. The Authority considers that Mr Howson acted recklessly as a

result.

The May Announcement

5.22.
The tenor of the May Announcement was that nothing had materially changed

since the March Results Announcement. This was reflected in its heading

(“Trading conditions unchanged”) and opening sentence (“Trading conditions

across the Group’s markets have remained largely unchanged since we announced

our 2016 full-year results”). This was not an accurate depiction of the Group’s

trading as at 3 May 2017, which was materially affected by the adverse and

deteriorating financial performance of CCS’s construction projects leading up to

that date. Mr Howson was closely involved in the drafting of this announcement.

5.23.
The facts and matters described above in relation to the December Announcement

and the March Results Announcement indicated a significant deterioration in the

financial performance of Carillion and CCS in particular. This deterioration

continued, with hard risk within CCS reported to Mr Howson and others as

increasing to £310.6 million by March 2017. Significant concerns were raised at

the Board meeting on 3 May 2017 attended by Mr Howson about the deterioration

in financial performance of Carillion’s major projects. These concerns were

consistent with the continued deterioration of CCS’s major projects, including (to

the knowledge of Mr Howson and another person):

(1)
RLUH, where in April 2017 the Project Team had estimated a £58.8 million

loss and a management adjustment of £64.9 million was applied to help

maintain the forecast profit margin of over £13 million;

(2)
Battersea, where in April 2017 the Project Team had forecast a £34.8

million loss and a management adjustment of just under £40 million was

applied to help maintain the forecast profit margin of over £8 million;

(3)
MMH, where in April 2017 the Project Team had forecast a £15.7 million

loss, with a management adjustment of £12.9 million applied to help

maintain a forecast profit margin of £17.7 million; and

(4)
AWPR, where in April 2017 Infrastructure had internally reported the most

likely end of life loss as being over £95 million, compared to the forecast

£10 million loss.

5.24.
The comment in the May Announcement about challenging contract positions did

not adequately address these matters. It was expressly linked to the similar

statement made in the March Results Announcement, which was specific to the

Middle East and Canada. This impression was reinforced by use of the words

“particularly in our international markets”. It therefore did not convey significant

problems within Carillion’s UK construction business (i.e. CCS).

5.25.
The Authority considers that Mr Howson and Carillion ought to have known that

the information in the May Announcement was false or misleading by reason of

the above matters. The Authority attributes the knowledge of Mr Howson and

another person to Carillion for its finding in this regard.

5.26.
By disseminating false or misleading information in circumstances where it ought

to have known the information was false or misleading, Carillion committed

market manipulation in breach of Article 15 of MAR. In the circumstances, and

by virtue of his knowledge and involvement in the May Announcement, Mr Howson

was knowingly concerned in Carillion’s breach of Article 15.

5.27.
The Authority considers that Mr Howson was aware that there was a risk that the

May Announcement was false or misleading due to the matters at paragraphs

5.14 to 5.17 and 5.22 to 5.24 above. He did not respond appropriately to this

risk and failed to take it properly into account when reviewing and approving the

May Announcement. He also failed to inform the Board and the Audit Committee

about these matters for the purpose of their review and approval of the May

Announcement. This is despite the fact that he must have been aware,

particularly having regard to the nature and cumulative effect of the information

he received from CCS management highlighting increasing levels of financial risks

and exposures associated with the financial performance of CCS’s construction

contracts and the number of occasions on which such information was reported

to him, that these matters would be highly relevant to their deliberations. The

Authority considers that Mr Howson acted recklessly as a result.

Carillion’s obligations and knowing concern

5.28.
Listing Rule 1.3.3R requires an issuer to take reasonable care to ensure that any

information it notifies to a RIS or makes available through the Authority is not

misleading, false or deceptive and does not omit anything likely to affect the

import of the information. As a listed company, Carillion was required to comply

with LR 1.3.3R.

5.29.
Section 91(2) of the Act provides that “If, in the case of a contravention [by an

issuer] … the [Authority] considers that [another person] who was at the material

time a director of [the issuer] was knowingly concerned in the contravention, it

may impose upon him a penalty of such amount as it considers appropriate.”

Carillion’s breaches and Mr Howson’s knowing concern

5.30.
By failing to take account of the matters at paragraphs 5.7 to 5.9, 5.14 to 5.17

and 5.22 to 5.24 above in its announcements, and by failing to ensure that the

matters at paragraphs 5.35 to 5.46 below in relation to Listing Principle 1 were

properly addressed, Carillion failed to take reasonable care to ensure that

information it notified to a RIS was not misleading, false or deceptive and did not

omit anything likely to affect the import of the information, in breach of LR 1.3.3R.

5.31.
By virtue of his knowledge and involvement in the Announcements as detailed

above, and by failing to ensure that the matters at paragraphs 5.33 to 5.46 below

in relation to Listing Principle 1 were properly addressed during the Relevant

Period, Mr Howson was knowingly concerned in Carillion’s breach of LR 1.3.3R

with regard to the Announcements.

5.32.
For the reasons given in paragraphs 5.12, 5.21 and 5.27 above, and in paragraph

5.47 below, the Authority considers that Mr Howson acted recklessly in respect of

his knowing concern in Carillion’s breach of LR 1.3.3R.

Carillion’s obligations and knowing concern

5.33.
Listing Principle 1 requires a listed company to take reasonable steps to establish

and maintain adequate procedures, systems and controls to enable it to comply

with its obligations. These obligations include compliance with the Listing Rules,

in particular the timely and accurate disclosure of information to the market, as

set out in LR 7.2.2G and LR 7.2.3G.

5.34.
As a listed company, Carillion was required to comply with Listing Principle 1.

Section 91(2) of the Act provides that “If, in the case of a contravention [by an

issuer] … the [Authority] considers that [another person] who was at the material

time a director of [the issuer] was knowingly concerned in the contravention, it

may impose upon him a penalty of such amount as it considers appropriate.”

Carillion’s procedures, systems & controls

5.35.
Throughout the Relevant Period, Mr Howson was the CEO of Carillion and his

responsibilities included working closely with the Group FD to ensure Carillion

communicated effectively with investors and had appropriate internal control

processes. Shortcomings in Carillion’s procedures, systems and controls around

the financial reporting of its construction contracts meant that Carillion was unable

to comply with its obligations under the Listing Rules.

5.36.
The Authority considers that a listed company should have in place procedures,

systems and controls that provide clear, consistent and transparent reporting

throughout the company. This should include procedures, systems and controls

that:

(1)
ensure the financial performance of construction contracts is assessed in

accordance with applicable accounting standards, including IAS 11;

(2)
identify and internally report on material financial risks associated with such

assessments;

(3)
produce consistent management and financial information about such

assessments and any associated risks, as well as ensuring that any

inconsistencies are identified and resolved with appropriate enquiry and

follow-up actions as required; and

(4)
provide sufficient information to the Board and the Audit Committee to

enable them properly to consider the financial performance of construction

projects and assess material risks associated with their financial reporting.

5.37.
Carillion’s procedures, systems and controls did not meet these standards. Mr

Howson was aware of and involved in the following matters that, when taken

together, made Carillion’s procedures, systems and controls inadequate during

the Relevant Period:

(1)
Significant pressure placed on CCS to meet targets;

(2)
Lack of proper records around contract accounting judgements;

(3)
Inconsistent management and financial information; and

(4)
Failure to inform the Board and the Audit Committee about the significant

financial risks being reported by CCS.

Pressure on CCS to meet targets

5.38.
Significant pressure was placed on CCS to meet very challenging budgeted and

reforecast targets through the budgeting and reforecasting process headed by

Carillion’s two executive directors, Mr Howson and the Group FD. The targets

were maintained even as CCS reported deteriorating financial performance in

certain major projects and increasing hard risks and MCS exposures during the

Relevant Period. This greatly increased the risk that contract accounting

judgements under IAS 11 would be applied too aggressively by CCS in order to

meet those targets and would not comply with IAS 11 as a result. In those

circumstances, the control framework around CCS’s contract accounting

judgements needed to be especially transparent and robust to minimise the risk

of non-compliance. It was not, significantly increasing the risk that market

announcements in relation to Carillion’s financial performance would not be

accurate.

5.39.
During the Relevant Period, despite knowing the pressure placed on CCS to meet

targets maintained by him, and despite his expertise in construction and contract-

related matters, Mr Howson did not take any meaningful steps to satisfy himself

that contract accounting judgements were being applied appropriately or to

ensure that the control framework around those judgements was sufficiently

transparent and robust to ensure compliance with IAS 11.

Lack of proper records

5.40.
The contract accounting judgements being applied were not properly documented,

which meant there was no clear and comprehensive record of the assessments

being made, approved or reviewed. This contributed to a lack of rigour around

contract accounting judgements and their approval and review. Mr Howson was

aware that the PRM process was a key forum at which the financial performance

of projects was discussed and reviewed at different levels within CCS, often in the

context of Carillion’s budgeting and reforecasting process. Mr Howson attended

the CCS PRMs during the Relevant Period, but there were no minutes taken of

PRM discussions and no record of any detailed review or changes to contract

account judgements made or the reasons for them.

Inconsistent management information on financial performance

5.41.
The management information produced and reported by CCS to (amongst others)

Mr Howson highlighted large and increasing risks associated with the reported

financial performance of CCS’s construction projects during the Relevant Period.

This information was inconsistent with other reports that contained much more

optimistic assessments of the financial performance of those projects. In

particular, Mr Howson was aware of the following matters during the Relevant

(1)
The increasingly large risks associated with the contract accounting

judgements being applied to CCS’s construction projects and underpinning

their financial performance were identified to Mr Howson by means of CCS

internally reporting on hard risk. This was seen by those making the

judgements as an increasingly important means of highlighting those risks

to enable appropriate action to be taken, for example by means of write-

offs, provisions or changes to budgets and reforecasts. Despite this, no

meaningful action was taken by Mr Howson in response.

(2)
The MCSs highlighted likely financial exposures associated with Carillion’s

contracts, including CCS’s construction projects. It was nonetheless another

means by which Business Divisions (including CCS) reported large

exposures that significantly increased during the Relevant Period. The

increasingly large exposures reported in it were not addressed by Mr

Howson.

(3)
There were large and increasing divergences during the Relevant Period

between the Project Teams’ assessments of the financial performance of the

Priority Contracts and the much more optimistic forecasts contained in

budgets and reforecasts. These divergences were reported to (amongst

others) Mr Howson by means of CCS PRMs or in some cases by email. Mr

Howson did not make proper enquiries as to the reasons behind these

divergences or seek to resolve them.

(4)
The above information provided to Mr Howson was inconsistent with the

figures reported to the Board and the Audit Committee in the MPSR

Executive Summaries and Overtrade Reports. It was also inconsistent with

the financial position of CCS’s construction projects, as typically reflected in

budgets and reforecasts. Mr Howson failed to undertake any enquiries to

understand why these inconsistencies had arisen and failed to take steps to

resolve them.

Failure to inform the Board and the Audit Committee

5.42.
The Board and the Audit Committee were not made aware of the significant and

increasing financial risks during the Relevant Period that were being highlighted

by CCS to (amongst others) Mr Howson, as described in paragraph 5.41 above.

This meant they were hampered in providing effective oversight of CCS’s financial

performance and the contract accounting judgements being applied to its major

projects. This was especially important for the Audit Committee since it was

responsible for reviewing and challenging whether Carillion had “followed

appropriate accounting standards and made appropriate estimates and

judgements [in its financial statements], taking into account the views of the

external auditor”.

5.43.
Instead, as Mr Howson was aware, reports to the Board (including his CEO

Reports) and discussions at Board meetings tended to focus on operational issues

associated with individual projects, not their financial impact. Financial reporting

to the Board in relation to financial risks associated with Carillion’s construction

contracts mainly consisted of the MPSR Executive Summaries (as approved by Mr

Howson during the Relevant Period) and Overtrade Reports. They did not reflect

the financial risks identified and highlighted by CCS by means of, for example,

hard risks, MCS exposures, CCS PRMs or otherwise.

5.44.
The information provided to the Audit Committee in order to enable them to

assess contract accounting judgements was contained in or appended to the

Group FD’s Report and the external auditors’ half and year-end memorandums.

These documents only reported the outcome of the judgements, not their basis

or the risks associated with them. As a result, and in the absence of information

about hard risks, MCS exposures and the adverse assessments made by Project

Teams (of which the external auditors were also not aware), they did not provide

the Audit Committee with information which was important in order effectively to

assess whether or not the judgements were being applied appropriately.

5.45.
In light of the above matters, the Authority considers that Carillion failed to take

reasonable steps to ensure that it had adequate procedures, systems and controls

during the Relevant Period to comply with its obligations under the Listing Rules.

Carillion breached Listing Principle 1 as a result.

5.46.
By virtue of his knowledge of the matters at paragraphs 5.35 to 5.45 above, and

his failure to ensure that they were properly addressed during the Relevant Period,

Mr Howson was knowingly concerned in Carillion’s breach of Listing Principle 1.

5.47.
Further, the Authority considers that Mr Howson was aware in light of the matters

at paragraphs 5.35 to 5.44 above that there was a risk that Carillion did not have

adequate procedures, systems and controls to enable it to comply with its

obligations under the Listing Rules. He did not respond appropriately to this risk

and failed to take any steps to address these matters during the Relevant Period.

The Authority considers that Mr Howson acted recklessly as a result.

5.48.
Premium Listing Principle 2 requires a listed company to act with integrity towards

the holders and potential holders of its premium listed securities.

5.49.
As a listed company, Carillion was required to comply with Premium Listing

Principle 2 in relation to its Premium listed securities during the Relevant Period.

5.50.
As explained in paragraphs 5.12, 5.21, 5.27, 5.32 and 5.47 above, Mr Howson

acted recklessly in relation to the facts and matters described above during the

Relevant Period. The Authority attributes his state of mind to Carillion in this

regard.

5.51.
For these reasons, Carillion breached Premium Listing Principle 2 by failing to act

with integrity towards its holders and potential holders of its premium listed

shares. Mr Howson was knowingly concerned in Carillion’s breach.

6.
SANCTION

Financial penalty

6.1.
The Authority’s policy for imposing a financial penalty is set out in Chapter 6 of

DEPP. In respect of conduct occurring on or after 6 March 2010, the Authority

applies a five-step framework to determine the appropriate level of financial

penalty. DEPP 6.5B and DEPP 6.5C set out the details of the five-step framework

that applies in respect of financial penalties imposed on individuals in non-market

abuse cases and market abuse cases respectively.

Step 1: disgorgement

6.2.
Pursuant to DEPP 6.5B.1G and DEPP 6.5C.1G, at Step 1 the Authority seeks to

deprive an individual of the financial benefit derived directly from the breach

where it is practicable to quantify this.

6.3.
The Authority has not identified any financial benefit that Mr Howson derived

directly from the breach.

6.4.
Step 1 is therefore £0.

Step 2: the seriousness of the breach

6.5.
Pursuant to DEPP 6.5B.2G and DEPP 6.5C.2G, at Step 2 the Authority determines

a figure that reflects the seriousness of the breach. That figure is based on a

percentage of the individual’s relevant income and, for market abuse cases, the

greater of that amount, a multiple of the profit or loss avoided by the individual

for his own benefit or £100,000 for cases the Authority has assessed as

seriousness level 4 or 5. The individual’s relevant income is the gross amount of

all benefits received by the individual from the employment in connection with

which the breach occurred, and for the period of the breach.

6.6.
The period of Mr Howson’s breach was 1 July 2016 to 10 July 2017. The Authority

considers Mr Howson’s relevant income for this period to be £1,326,187. The

Authority considers that Mr Howson did not make a direct profit or avoid a loss as

a result of his knowing concern in Carillion’s breaches of Article 15 of MAR, and

therefore DEPP 6.5C.2G(b) does not apply.

6.7.
In deciding on the percentage of the relevant income that forms the basis of the

Step 2 figure, the Authority considers the seriousness of the breach and chooses

a percentage between 0% and 40%. This range is divided into five fixed levels

which represent, on a sliding scale, the seriousness of the breach; the more

serious the breach, the higher the level. For penalties imposed on individuals in

non-market abuse and market abuse cases there are the following five levels:

Level 1 – 0%

Level 2 – 10%

Level 3 – 20%

Level 4 – 30%

Level 5 – 40%

Level of seriousness

6.8.
In assessing the seriousness level, the Authority takes into account various factors

which reflect the impact and nature of the breach.

72

Impact of the breach

6.9.
DEPP 6.5B.2G(8) and DEPP 6.5C.2G(11) set out factors relating to the impact of

a breach. The Authority considers the following factors to be relevant to Mr

Howson’s knowing concern in Carillion’s breaches:

(1) Mr Howson did not personally financially benefit from the breaches;

(2) the breaches had a seriously adverse effect on the orderliness of, or

confidence in, the market. The public nature of Carillion’s business, the size

and scope of its reporting failures and its subsequent liquidation have

together undermined public confidence in the financial reporting regime,

including the listing regime; and

(3) the breaches meant that Carillion’s shares were significantly overpriced for

a considerable period. Following the announcement of 7 July 2017, which

included the £375 million construction services provisions, Carillion’s share

price fell 39% by the end of the day.

Nature of the breach

6.10.
DEPP 6.5B.2G(9) and DEPP 6.5C.2G(12) set out factors relating to the nature of

a breach. Of these, the Authority considers the following factors to be relevant to

Mr Howson’s knowing concern in Carillion’s breaches:

(1) The breaches revealed serious and systemic weaknesses in Carillion’s

procedures and/or in the management systems or internal controls relating

to Carillion’s business.

(2) The breaches of LR 1.3.3R and Listing Principle 1, in respect of which Mr

Howson was knowingly concerned, continued for a period of over a year

and resulted in the misleading Announcements.

(3) Mr Howson held a senior position within Carillion as its CEO.

(4) As CEO Mr Howson held a position of trust for investors, creditors and

employees of Carillion, all of whom were entitled to rely on the

announcements being made by Carillion.

(5) Mr Howson was an experienced manager in the construction services

sector.

6.11.
DEPP 6.5B.2G(12) and DEPP 6.5C.2G(15) set out factors which are likely to be

considered ‘level 4 factors’ or ‘level 5 factors’. The Authority considers the

following factors to be relevant to the breaches:

(1) The breaches caused a significant loss or risk of loss to individual

consumers, investors or other market users.

(2) The breaches resulted in an effect on the orderliness of, or confidence in,

markets.

(3) Mr Howson breached a position of trust.

(4) The breaches were committed recklessly.

6.12.
DEPP 6.5B.2G(13) and DEPP 6.5C.2G(16) lists factors likely to be considered ‘level

1, 2 or 3 factors’. Of these, the Authority considers the following factor to be

relevant to the breaches:

(1) No profits were made or losses avoided by Carillion as a result of the

breaches, either directly or indirectly.

6.13.
Taking all of these factors into account, the Authority considers the seriousness

of the breaches to be level 4 and so the Step 2 figure is 30% of £1,326,187, which

equates to £397,856.

Step 3: mitigating and aggravating factors

6.14.
Pursuant to DEPP 6.5B.3G and DEPP 6.5C.3G, at Step 3 the Authority may

increase or decrease the amount of the financial penalty arrived at after Step 2,

but not including any amount to be disgorged as set out in Step 1, to take into

account factors which aggravate or mitigate the breach.

6.15.
The Authority considers that there are no aggravating or mitigating factors.

6.16.
Step 3 is therefore £397,856.

Step 4: adjustment for deterrence

6.17.
Pursuant to DEPP 6.5B.4G and 6.5.C.4G, if the Authority considers the figure

arrived at after Step 3 is insufficient to deter the individual who committed the

breach, or others, from committing further or similar breaches, then the Authority

may increase the penalty.

6.18.
The Authority considers that the Step 3 figure of £397,856 represents a sufficient

deterrent to Mr Howson and others, and so has not increased the penalty at Step

4.

6.19.
Step 4 is therefore £397,856.

Step 5: settlement discount

6.20.
Pursuant to DEPP 6.5B.5G, if the Authority and the individual on whom a penalty

is to be imposed agree the amount of the financial penalty and other terms, DEPP

6.7 provides that the amount of the financial penalty which might otherwise have

been payable will be reduced to reflect the stage at which the Authority and the

individual reached agreement. The settlement discount does not apply to the

disgorgement of any benefit calculated at Step 1.

6.21.
No settlement discount applies.

6.22.
Step 5 is therefore £397,800 (rounded down to the nearest £100 in accordance

with the Authority’s usual practice).

6.23.
The Authority therefore has decided to impose a financial penalty of £397,800 on

Mr Howson.

7.
REPRESENTATIONS

7.1.
Annex B contains a brief summary of the key representations made by Mr Howson

and how they have been dealt with. In making the decision which gave rise to

the obligation to give this Notice, the Authority has taken into account all of the

representations made by Mr Howson, whether or not set out in Annex B.

8.
PROCEDURAL MATTERS

8.1.
This Notice is given to Mr Howson under sections 127 and 92 of the Act and in

accordance with section 388 of the Act.

8.2.
The following statutory rights are important.

Decision maker


8.3.
The decision which gave rise to the obligation to give this Notice was made by the

RDC. The RDC is a committee of the Authority which takes certain decisions on

behalf of the Authority. The members of the RDC are separate to the Authority

staff involved in conducting investigations and recommending action against firms

and individuals. Further information about the RDC can be found on the

Authority’s website:

The Tribunal


8.4.
Mr Howson has the right to refer the matter to which this Notice relates to the

Tribunal. Under paragraph 2(2) of Schedule 3 of the Tribunal Procedure (Upper

Tribunal) Rules 2008, Mr Howson has 28 days from the date on which this Notice

is given to him to refer the matter to the Tribunal. A reference to the Tribunal is

made by way of a signed reference notice (Form FTC3) filed with a copy of this

Notice. The Tribunal’s contact details are: The Upper Tribunal, Tax and Chancery

9730; email: fs@hmcts.gsi.gov.uk). Further information on the Tribunal,

including guidance and the relevant forms to complete, can be found on the HM

Courts and Tribunal Service website:

8.5.
A copy of the reference notice (Form FTC3) must also be sent to the Authority at

the same time as filing a reference with the Tribunal. It should be sent to Stephen

Robinson at the Financial Conduct Authority, 12 Endeavour Square, London E20

1JN.

8.6.
Once any such referral is determined by the Tribunal and subject to that

determination, or if the matter has not been referred to the Tribunal, the Authority

will issue a final notice about the implementation of that decision.

Access to evidence


8.7.
Section 394 of the Act applies to this Notice.

8.8.
The person to whom this Notice is given has the right to access:

76

(1)
the material upon which the Authority has relied in deciding to give this

Notice; and

(2)
the secondary material which, in the opinion of the Authority, might

undermine that decision.

Confidentiality and publicity


8.9.
This Notice may contain confidential information and should not be disclosed to a

third party (except for the purpose of obtaining advice on its contents). In

accordance with section 391 of the Act, a person to whom this Notice is given or

copied may not publish the Notice or any details concerning it unless the Authority

has published the Notice or those details.

8.10.
However, the Authority must publish such information about the matter to which

a decision notice or final notice relates as it considers appropriate. The person to

whom this Notice is given or copied should therefore be aware that the facts and

matters contained in this Notice may be made public.

Authority contact


8.11.
For more information concerning this matter generally, contact Stephen Robinson

at
the
Authority
(direct
line:
020
7066
1388/email:

Stephen.Robinson@fca.org.uk).

Tim Parkes
Chair, Regulatory Decisions Committee


ANNEX A

RELEVANT STATUTORY AND REGULATORY PROVISIONS

The statutory and regulatory provisions set out below are the versions that were

in force in the period between 1 July 2016 and 10 July 2017 (i.e. the Relevant

1.
STATUTORY PROVISIONS

1.1.
The Authority’s general duties established in section 1B of the Act include the

strategic objective of ensuring that relevant markets function well and the

operational objectives of protecting and enhancing the integrity of the UK financial

system and securing an appropriate degree of protection for consumers.

Power to Impose Penalties for Market Abuse

1.2.
Section 123 of the Act sets out the Authority’s power to impose penalties in cases

of market abuse. It states as follows:

“(1) The [Authority] may exercise its power under subsection (2) if it is satisfied

that—




(a) a person has contravened […] Article 15 (prohibition of market

manipulation) of the market abuse regulation;

(2) The [Authority’s] power under this subsection is a power to impose a

penalty of

such amount as it considers appropriate on the person.”

Individual Liability for Legal Persons under MAR

1.3.
Section 131AD of the Act sets out the provisions for individual liability in respect

of legal persons under Article 12 of MAR. It states as follows:

“(1) An individual participates in a decision by a body corporate for the purposes

of […] Article 12.4 (market manipulation) of the market abuse regulation

where—

(a) the individual was an officer of the body corporate when the decision was

made; and

(b) the [Authority is] satisfied that the individual was knowingly concerned in

the decision.

(2) In this section “officer”, in relation to a body corporate, means–

(a) a director, member of the committee of management, chief executive,

manager, secretary or other similar officer of the body, or a person purporting

to act in any such capacity; or

(b) an individual who is a controller of the body.”

Listing Rules Statutory Provision

Power to Impose Penalties for Breach of Listing Rules Provisions

1.4.
Section 91 of the Act states as follows:

“(1) If the [Authority] considers that-

(a) an issuer of listed securities, or

(b) an applicant for listing,

has contravened any provision of listing rules, it may impose on him a penalty of

such amount as it considers appropriate.

(2) If, in the case of a contravention by a person referred to in subsection (1)

[(“P”)], the [Authority] considers that another person who was at the material

time a director of P was knowingly concerned in the contravention, it may impose

upon him a penalty of such amount as it considers appropriate.”

2.
REGULATORY PROVISIONS

Market Abuse Regulation (EU No. 596/2014)

Market Manipulation








2.1.
Article 12(1)(c) of MAR states that market manipulation will comprise of the

following activities:

“disseminating information through the media, including the internet, or by any

other means, which gives, or is likely to give, false or misleading signals as to the

supply of, demand for, or price of, a financial instrument, a related spot

commodity contract or an auctioned product based on emission allowances or

secures, or is likely to secure, the price of one or several financial instruments, a

related spot commodity contract or an auctioned product based on emission

allowances at an abnormal or artificial level, including the dissemination of

rumours, where the person who made the dissemination knew, or ought to have

known, that the information was false or misleading”.

2.2.
Article 12(4) of MAR states as follows:

“Where the person referred to in this Article is a legal person, this Article shall

also apply, in accordance with national law, to the natural persons who participate

in the decision to carry out activities for the account of the legal person

concerned.”

2.3.
Article 15 of MAR states as follows:

“A person shall not engage in or attempt to engage in market manipulation.”

2.4.
Listing Rule 1.3.3R states as follows:

“An issuer must take reasonable care to ensure that any information it notifies to

a RIS or makes available through the [Authority] is not misleading, false or

deceptive and does not omit anything likely to affect the import of the

information”.

2.5.
Listing Principle 1 states as follows:

“A listed company must take reasonable steps to establish and maintain

adequate procedures, systems and controls to enable it to comply with its

obligations.”

Guidance on the Listing Principles






2.6.
LR 7.2.2 G states as follows:

“Listing Principle 1 is intended to ensure that listed companies have adequate

procedures, systems and controls to enable them to comply with their

obligations under the listing rules, disclosure requirements, transparency rules

and corporate governance rules. In particular, the [Authority] considers that

listed companies should place particular emphasis on ensuring that they have

adequate procedures, systems and controls in relation to, where applicable:

(2) the timely and accurate disclosure of information to the market.”

2.7.
LR 7.2.3 G states as follows:

“Timely and accurate disclosure of information to the market is a key obligation

of listed companies. For the purposes of Listing Principle 1, a listed company

should have adequate systems and controls to be able to:

(1) ensure that it can properly identify information which requires disclosure

under the listing rules, disclosure requirements, transparency rules or corporate

governance rules in a timely manner; and

(2) ensure that any information identified under (1) is properly considered by

the directors and that such a consideration encompasses whether the

information should be disclosed.“

2.8.
Premium Listing Principle 2 states as follows:





“A listed company must act with integrity towards the holders and potential

holders of its premium listed securities.”

Decision Procedures and Penalties Manual

2.9.
In determining the level of financial penalty to be paid in respect of conduct

occurring on or after 6 March 2010 the Authority has had regard to the provisions

of DEPP, particularly DEPP 6.5B and DEPP 6.5C.

ANNEX B

REPRESENTATIONS

1. A summary of the key representations made by Mr Howson, and the Authority’s

conclusions in respect of them (in bold), is set out below.

Knowing concern – the law

2. The case law is clear that knowing concern requires actual involvement in the

contravention and actual knowledge of all constitutive facts necessary to establish a
contravention by the alleged primary contravenor (i.e. Carillion), yet it is not even
alleged that Mr Howson had such knowledge, let alone established.

3. Mr Howson’s position on knowing concern is supported by the recent decision by the

Court of Appeal in Ferreira3. The Court of Appeal considered that policy reasons which
the Authority has raised in support of its construction of knowing concern were not
persuasive and rejected the suggestion that personal liability could be imposed on
directors simply on the basis that they knew of the actions that the company was
taking. The Court of Appeal’s decision makes it clear that there is intended to be a
difference in the test for liability for a primary infringer and a secondary party.

4. In order for Mr Howson to be knowingly concerned in a contravention by

Carillion of Article 15 of MAR, LR 1.3.3R, Listing Principle 1 and/or Premium
Listing Principle 2, he must be shown: (i) to have been actually involved in
the contravention; and (ii) to have had “knowledge of the facts upon which
the contravention depends”4. As explained below in respect of each specific
contravention, the Authority disagrees with Mr Howson’s view as to what (ii)
requires the Authority to establish.

5. The Court of Appeal’s decision in Ferreira is not inconsistent with the

Authority’s analysis of the knowingly concerned test. In Ferreira, the Court
of Appeal was considering a contravention which included a disapplication
provision (i.e. a provision identifying the circumstances in which the
contravention does not apply) and a factual element relating to that
disapplication provision, but no equivalent disapplication provision or factual
element exists in relation to the contraventions in this case. As Ferreira was
concerned with knowledge of a purely factual question, it does not support
Mr Howson’s interpretation of the knowingly concerned test, which effectively
requires him to have had knowledge of legal conclusions or evaluations, as
opposed to primary facts. The Court of Appeal’s analysis of the relevant policy
arguments arose in the context of a primary offence of strict liability;
fundamentally different considerations apply in this case, where the primary
contraventions are fault-based. As the primary contraventions in this case are
established by reference to the knowledge of Mr Howson and others who are
alleged to be knowingly concerned in the breach, in the Authority’s view there
is no rationale for including a requirement of additional knowledge on the part
of the secondary party.

6. In respect of Article 15 of MAR, the constitutive parts of the alleged contravention

which it is necessary for Mr Howson to have known are that each Announcement gave
or was likely to give false or misleading signals as to the price of Carillion’s shares, and
that Carillion ought to have known that the information was false or misleading.

3 FCA v Ferreira [2022] EWCA Civ 397
4 SIB v Scandex Capital Management A/S [1998] 1 WLR 712

7. The falsity of the Announcements is clearly a constitutive part of Carillion’s alleged

breach, and therefore a fact which Mr Howson must be shown to have known. Article
12(1)(c) of MAR is clear that the first requirement to engage the provision is the
dissemination of information which gives, or is likely to give, false or misleading signals
as to the price of a financial instrument. The secondary question is then whether the
person who made the dissemination knew or ought to have known that the information
was false or misleading. Carillion cannot have known that an Announcement was false
unless it was in fact false; similarly, it cannot be said that Carillion ought to have known
that an Announcement was false unless it was in fact false. If the Announcements
were entirely true, it could not be alleged that Carillion had committed market
manipulation.

8. The Authority’s submission that whether information is false or misleading is a legal

assessment and therefore not a constitutive fact is not convincing. The Authority is
also wrong to submit that the consequence of Mr Howson’s interpretation of the law
would be that directors of a listed company could remain passive in response to
warning signs. A director could be fixed with knowledge by way of wilful blindness or
as a matter of evidence. It cannot be right for a person to be exposed to potentially
unlimited fines for being “knowingly concerned” in wrongdoing of which they have no
knowledge; Mr Howson’s interpretation is fair because it means that directors who
know that there has been misinformation to investors will be caught by the regime but
those who are innocent, like Mr Howson, will not be.

9. The Authority does not agree with Mr Howson’s view as to what is required in

order for him to have had knowledge of the facts upon which Carillion’s
contravention of Article 15 of MAR depends. Instead, the Authority considers
that, in respect of each Announcement, it is necessary to show that Mr
Howson knew: (i) the information contained in the Announcement; and (ii)
sufficient facts to support the conclusion that Carillion ought to have known
that the Announcement was false or misleading.

10. If Mr Howson’s submission was correct, the Authority would effectively have

to show that he acted deliberately. The Authority considers that is not the
correct test. Carillion’s breach of Article 15 of MAR is based on the attribution
of knowledge from Mr Howson (and others) to Carillion, as a result of which
Carillion ought to have known that the Announcements were false or
misleading. There is no need to prove actual knowledge that the
Announcement in question was false or misleading for the purpose of
Carillion’s primary contravention. Likewise, there is no need to establish that
Mr Howson had such knowledge in order for him to be knowingly concerned.

11. The proposition that information is “false or misleading” is not a primary fact,

but rather a legal conclusion reached by applying the relevant legal test to
the facts. Instead, the facts relied upon in respect of Carillion’s
contraventions of Article 15 of MAR are facts concerned with the
Announcements and, by contrast, what was said and known within Carillion
as to the matters addressed in the Announcements, for example, the financial
risks and exposures reported as high risks and likely major contract
exposures.

12. Further, Mr Howson’s approach to the knowingly concerned test would

fundamentally undermine the market abuse regime and its objectives, as,
notwithstanding Mr Howson’s submissions, the implication would be that a
director could remain passive in response to warning signs, so as to avoid
acquiring actual knowledge that an announcement contained false or
misleading information, and thereby insulate himself/herself from individual
liability. In addition, if a director did not have the personal responsibility to
take steps to satisfy himself/herself that information is true and not
misleading, the obligation on a company to take reasonable care in respect of

its announcements would be significantly undermined. In the Authority’s
view, it is not unfair for a director of a listed issuer to be held to be knowingly
concerned in circumstances where it is their own conduct which gives rise or
contributes to the primary breach.

13. In respect of LR 1.3.3R, the constitutive parts of the alleged contravention which it is

necessary for Mr Howson to have known are that the information in the Announcement
was misleading, false or deceptive or omitted things likely to affect the import of the
information, and that Carillion had failed to take reasonable care to ensure that the
Announcement was not misleading, false or deceptive and did not omit things likely to
affect the import of the information.

14. The fact that the Announcements were misleading is a constitutive part of the

contravention. LR 1.3.3R is in the Handbook under the heading “Misleading
information not to be published”, so if the published information is not misleading, the
rule is not engaged. LR 1.3.3R clearly ties the obligation to take reasonable care to
the notification to the RIS or making available through the Authority information that
is not false or misleading. Absent such a notification, the rule cannot be breached.

15. It must also be shown that Carillion failed to take reasonable care to ensure that the

Announcements were not false or misleading. This is a constitutive fact and therefore
a fact which Mr Howson must be shown to have known for knowing concern to be made
out. Alternatively, it must at the very least be shown that Mr Howson knew all of the
facts upon which such a conclusion is based.

16. It is not sufficient to show that Mr Howson simply knew facts that were inconsistent

with the information in the Announcements. That cannot be equated with knowledge
that the Announcements were misleading.

17. The Authority does not agree with Mr Howson’s view as to what is required in

order for him to have had knowledge of the facts upon which Carillion’s
contravention of LR 1.3.3R depends. Similar to Article 15 of MAR, the matters
which Mr Howson submits he requires knowledge of in order to be knowingly
concerned are legal conclusions, rather than primary facts.

18. Instead, the Authority considers that Mr Howson was knowingly concerned in

Carillion’s contravention of LR 1.3.3R because he knew the following facts: (i)
the information contained in the Announcements; (ii) information (such as
that contained in MCSs on potential exposures in the Priority Contracts) which
indicated that the statements in the Announcements regarding Carillion’s
financial position did not reflect the true financial performance of CCS’s
construction contracts; and (iii) the (inadequate) steps taken by Carillion
during the Relevant Period to ensure that the Announcements were not false
or misleading, which included knowledge that the Board and the Audit
Committee were not provided with the above information (which in turn
hampered their ability to ensure that the Announcements were accurate).

19. The Authority considers that, for the reasons set out in this Notice, the

Announcements clearly were misleading, but does not consider it is necessary
to show that Mr Howson knew this or that the steps taken by Carillion to
ensure that the Announcements were not misleading were inadequate. As
with Article 15 of MAR, if the Authority was required to establish such
knowledge, it would effectively be required to prove that he acted
deliberately, which the Authority considers goes too far and is not the correct
test.

20. In respect of Listing Principle 1, the constitutive parts of the alleged contravention

which it is necessary for Mr Howson to have known include that Carillion had not taken

reasonable steps to establish and maintain adequate procedures, systems and controls
to enable it to comply with its obligations.

21. The Authority does not agree with Mr Howson’s view as to what is required in

order for him to have had knowledge of the facts upon which Carillion’s
contravention of Listing Principle 1 depends. Instead, the Authority considers
it is only necessary to establish that Mr Howson knew of the (inadequate)
steps taken by Carillion during the Relevant Period to seek to establish and
maintain adequate procedures, systems and controls to enable it to comply
with its obligations. The Authority does not consider it is necessary for it to
establish that Mr Howson knew that those steps fell short of what reasonable
care required; that is a legal conclusion and not a primary fact.

22. In respect of Premium Listing Principle 2, the constitutive facts which it is necessary

for Mr Howson to have known are that Carillion acted with a lack of integrity towards
the holders and potential holders of its securities.

23. On the facts of this case, it is implicit that a lack of integrity must at least involve

knowledge that the Announcements were false or misleading.

24. Carillion’s contravention of Premium Listing Principle 2 is based on attributing

the knowledge of Mr Howson (and others) to Carillion. The facts which
constitute Carillion’s contravention are therefore that Mr Howson (and
others) appreciated the risk of Carillion committing breaches of Article 15 of
MAR, LR 1.3.3R and Listing Principle 1 and did not respond appropriately to
that risk. In order to be knowingly concerned in Carillion’s contravention, the
Authority must show that Mr Howson had the knowledge that gives rise to
Carillion’s integrity breach, i.e. that he knew of the risk of breach, and that he
did not respond appropriately to that risk. The Authority therefore does not
agree that it is necessary to show that Mr Howson knew that the
Announcements were false or misleading and that Carillion acted with a lack
of integrity.

Knowing concern - the allegations

25. To the extent that any breach by Carillion depends on additional matters not alleged

against Mr Howson, no finding of knowing concern should be made against him.

26. In respect of all of the breaches, the Authority has reached the view that Mr

Howson’s knowledge is sufficient to conclude that Carillion was in breach,
even where Carillion was also in breach as a result of facts known by others.

27. The necessary constitutive facts have not been alleged to make out the knowing

concern allegations. Alternatively, Mr Howson denies the factual matters relied on to
meet the test for knowing concern.

28. Mr Howson did not know the facts that meant the Announcements contained

information giving or likely to give false or misleading signals as to Carillion’s share
price. It is also denied that he ought to have known that the Announcements were
false or misleading.

29. The Authority considers that Mr Howson was aware of information and

warning signs which indicated that the positive statements in the
Announcements did not reflect the true financial performance of CCS’s
construction contracts and that, as a result, he ought to have been aware that
the information in the Announcements was false or misleading. As a result of
his knowledge and involvement in the Announcements, the Authority
considers that Mr Howson was knowingly concerned in Carillion’s breaches of
Article 15 of MAR.

Listing Rule 1.3.3R and Listing Principle 1

30. Mr Howson had a large amount of information to support his belief that the

Announcements were accurate. He did not know that the control framework was at
risk of failing.

31. The Authority considers that Mr Howson’s submission fails to take into

account the information and warning signs he received, as a result of which
he ought to have known that the information in the Announcements was false
or misleading. Further, Mr Howson was aware that the Board and the Audit
Committee were not made aware of this information and the warning signs,
that inconsistent management information on financial performance was
being produced, and that the contract accounting judgements being applied
were not properly documented, and so the Authority considers he must have
been aware there was a risk that Carillion did not have adequate procedures,
systems and controls to enable it to comply with its obligations under the
Listing Rules.

Recklessness and lack of integrity

32. Mr Howson did not behave recklessly. He placed reasonable trust in the personnel,

processes and procedures, and whenever an issue was raised with him (for example,
negative accruals), he sought to address it. Many of the matters referred to were
considered by other Board members, and he relied on the systems and procedures in
place, the implementation of which was not his responsibility.

33. In any case, it is not accepted that a finding of a lack of integrity necessarily follows

on from a finding of recklessness. A finding of a lack of integrity requires something
more than recklessness. The Tribunal has stated5 that in its view integrity “connotes
moral soundness, rectitude and steady adherence to an ethical code. A person lacks
integrity if unable to appreciate the distinction between what is honest or dishonest by
ordinary standards.” It cannot be said that Mr Howson is unable to appreciate the
distinction between what is honest and dishonest by ordinary standards, but this is
what would be required for an allegation of a lack of integrity to be established.

34. The Authority considers, for the reasons set out in this Notice, that Mr Howson

was aware of the risk that the Announcements were false or misleading, and
that he acted recklessly by failing to respond appropriately to this risk, by
failing to take it into account when reviewing and approving the
Announcements and by failing to inform the Board and the Audit Committee
of the warning signs of which he was aware. Further, for the reasons set out
in this Notice, the Authority considers that Mr Howson was also aware of the
risk that Carillion did not have adequate procedures, systems and controls to
enable it to comply with its obligations under the Listing Rules, and that he
acted recklessly by not responding appropriately to this risk and by failing to
take any steps to address the various issues relating to Carillion’s procedures,
systems and controls. Given Mr Howson’s knowledge and responsibilities, the
Authority does not consider that it was reasonable for him simply to rely on
others to address issues or on Carillion’s systems and procedures which were
in place.

35. The Authority considers that it is well-established that recklessness can

constitute a lack of integrity6, and that Mr Howson’s reckless conduct
demonstrates an objective failing of ethics or morals on his part and thereby
a lack of integrity. In respect of the breach of Article 15 of MAR, recklessness
on the part of a CEO of a listed company as to the accuracy of its market
announcements is, objectively, an ethical or moral failing. Shareholders and

5 Ghanshyam Batra v The Financial Conduct Authority [2014] UKUT 0214 (TCC)
6 See, for example, Tariq Carrimjee v The Financial Conduct Authority [2015] UKUT 0079 (TCC)

potential shareholders rely on the accuracy of market announcements. For Mr
Howson to sign off on positive market announcements despite clear warning
signs about significant deterioration in the performance of the company is a
serious form of recklessness. Further, in respect of the breaches of LR 1.1.3R
and Listing Principle 1, Mr Howson’s failings included a failure to ensure that
the Board and the Audit Committee were informed of the warning signs of
which he was aware, in circumstances where he knew that these warning
signs were inconsistent with other management and financial information
provided to Carillion. The Authority considers that Mr Howson’s recklessness
in this regard amounts to a lack of integrity.

Mr Howson’s roles and responsibilities

36. Mr Howson was appointed by the Board because it wanted an operationally focused

CEO. He had never worked in the Finance function and he was not appointed to make
complex contract accounting judgements for large construction projects. He had a
heavy workload managing those matters within his remit and was entitled to expect
significant issues to be raised with him. In practice, he dealt with a broad range of
operational issues on major contracts, whilst the Group FD provided leadership from a
finance perspective.

37. The Group FD was responsible for the financial affairs of the Group and for accurately

reporting the financial results to the market, ensuring adequate internal financial
reporting and ensuring that there were adequate systems, controls and procedures
around financial reporting. These were not Mr Howson’s responsibilities and he placed
trust in Mr Adam and Mr Khan, both of whom were well respected, experienced
professionals.

38. Mr Howson did not decide the traded value of contracts and was not responsible for

ensuring compliance with IAS 11. Determining the amounts to be traded on Carillion’s
construction contracts depended on subjective judgements by the Commercial and
Finance functions within CCS. Those judgements were subject to a process of review
and approval within CCS. Mr Howson did not play a part in making those judgements;
that was the responsibility of individuals within CCS and CCS’s Finance Director who
reported to the Group FD. The Group FD was also responsible for the profit recognition
policy. Those responsible for the relevant contract accounting judgements, including
the Group FD, were all aware of the alleged warnings of which Mr Howson was aware.
Simply having knowledge of a contract would not have equipped Mr Howson to
overturn the necessary judgements made, especially given the volume of contracts
that Carillion had, and in any event that was not his role.

39. If there were any concerns that the traded positions did not reflect the true contract

positions or were not in accordance with IAS 11, it was reasonable for Mr Howson to
have expected the CCS Finance Director and/or the Group FD to have dealt with them.
He also had every reason to believe that the external auditors and the Audit Committee
would have had access to relevant documents.

40. Mr Howson and the Group FD were the only executive directors at Board level.

Carillion’s Annual Report for 2016 shows that Mr Howson’s responsibilities
included working closely with the Group FD to ensure that the Group had in
place appropriate risk management and internal control processes and
maintained effective relationships and communications with investors. Mr
Howson could therefore not reasonably fail to inform the Board and the Audit
Committee of the warning signs regarding CCS’s financial position of which
he was aware.

41. Mr Howson received a number of warning signs and knew that the Board and

the Audit Committee were unaware of them. He also knew that the Board and
the Audit Committee had instead received much more positive information
about the financial performance of major contracts. As part of his

responsibilities regarding Carillion’s internal control processes, Mr Howson
needed to ensure that not just the Group FD but also the Board and the Audit
Committee were informed of the warning signs that he received, so that they
could provide effective oversight of Carillion’s business and the risks in that
business, including those associated with its financial reporting to the
market.

42. The fact that Mr Howson was expected to work closely with the Group FD was

particularly important in respect of IAS 11 accounting judgements, as they
are underpinned by an assessment of the expected performance of the
construction contracts in question. Mr Howson had considerable experience
of Carillion’s business and also had operational experience around
challenging contracts and specific knowledge of the Priority Contracts. He
was therefore particularly well-equipped to apply appropriate scrutiny to the
commercial assessments which underpinned Carillion’s IAS 11 accounting
judgements and financial reporting. It was not reasonable for him to rely
exclusively on the Finance and audit functions and fail to challenge or make
further enquiries in the face of the information and warning signs that he
received.

Carillion’s procedures, systems and controls

43. Carillion had extensive systems, controls and procedures around financial reporting,

including external auditors, the Audit Committee and an experienced Group FD. Mr
Howson was not responsible for ensuring these systems and controls were adequate,
and he did not consider them to be inadequate.

44. Mr Howson does not accept that the challenges and targets set gave rise to a clear risk

that accounting judgements would not comply with IAS 11 and would misreport the
financial performance of major projects. Alternatively, he denies having any knowledge
of this.

45. The Authority has accepted that Carillion’s financial reporting policies and procedures

were adequate, that the pressure put on CCS was not untoward, and that Mr Howson
did not set the targets in question. It was not Mr Howson’s role to police the control
framework, and he had good reasons to consider that there was a robust control
framework in place, so the allegation in respect of the pressure put on CCS is not made
out.

46. As far as Mr Howson could reasonably have known, the contract accounting

judgements were made by the relevant personnel in accordance with Carillion’s policies
and procedures and were not made arbitrarily. He also took steps to satisfy himself
that the contract accounting judgements were being applied appropriately.

47. The Authority considers that there were serious failings in Carillion’s systems

and controls during the Relevant Period. In particular, there was
inconsistency between the information reported by CCS which highlighted
large and increasing risks, and the much more optimistic assessment set out
in other reports, such as the Overtrade Reports and MPSRs, that were
provided to the Board and the Audit Committee. Mr Howson was aware of
these inconsistencies, but he failed to undertake any enquiries to understand
why they had arisen or take any steps to resolve them. Given the warning
signs known to Mr Howson, he must have appreciated the risk that Carillion’s
systems and controls were therefore inadequate.

48. The Authority considers that the evidence shows that there was significant

pressure on CCS to meet very challenging financial targets, in the face of clear
warning signs that CCS’s business was deteriorating significantly. This
pressure, whilst not itself undue, was an important factor which necessitated
a robust control framework to ensure that inappropriate contract accounting
judgements were not made in consequence.

49. Mr Howson’s submissions that it was not his role to police the control

framework, and that others were responsible for the relevant contract
accounting judgements, ignore the fact that he had a responsibility to work
closely with the Group FD to ensure that the Group had in place appropriate
risk management and control processes, and fail to take account of the fact
that he was aware of the demanding nature of the targets set and the
pressure placed on CCS to meet them during the Relevant Period.

50. Mr Howson was present at PRMs in which budgets and forecasts were

discussed and he received emails in which the challenging nature of targets
set were communicated. He was also aware of the impact of the pressure to
meet the targets on the accounting judgements of those within CCS, as
reflected in the increasing disparity between the end-of-life forecasts of
Project Teams and the traded figures for the Priority Contracts, and the
increasing management adjustments applied in order to meet the targets set.
This disparity and the management adjustments applied were reported in
various CCS PRMs, attended by Mr Howson, during the Relevant Period. In
the light of his knowledge and exposure to these matters, and his
responsibilities regarding Carillion’s risk management and control processes,
Mr Howson could not reasonably ignore the risk that contract accounting
judgements under IAS 11 would be applied by CCS too aggressively in
response to the pressure it was under and he could not reasonably assume
without further enquiry and challenge that there was a robust control
framework in place.

Management adjustments

51. Management adjustments were necessary to ensure that the figures were reported

accurately. They were a legitimate part of construction contract accounting and
provided for under the profit recognition policy. That policy forbade arbitrary
management adjustments, not management adjustments per se.

52. There is no evidence that Mr Howson was aware of management adjustments being

used for an improper purpose. It was reasonable for him to assume that the rationale
and reasons for any trading judgements would be in the Position Paper that would be
accessed by the external auditors and Finance. He could therefore assume that if any
reviewer was not satisfied with a justification, it would be raised with the relevant
Business Unit or Business Division, or if material with the Audit Committee.

53. Mr Howson attended a series of CCS PRMs in 2017 which showed that the

Project Teams’ forecasts for the Priority Contracts continued to deteriorate,
and yet the scale of management adjustments continued to increase, such
that the traded figures for the projects remained unaltered. Despite being
aware of: the Project Team’s estimates for each of the Priority Contracts (and
the continued deterioration of those estimates); the large and increasing
divergence from the traded figures for each project; and the correspondingly
large and increasing management adjustments applied to each project, such
that the traded figures remained unaltered, Mr Howson made no enquiries to
satisfy himself that such large and increasing management adjustments were
warranted. The importance of doing so is clear from the fact that the
management adjustments in respect of the Priority Contracts amounted (in
each of the CCS PRMs between March and June 2017) to over half of the
underlying PBT for the Group for full year 2016, as reported to the market in
the March Results Announcement.

54. In these circumstances, it was not reasonable for Mr Howson simply to have

assumed that the rationale for management adjustments would be explained
to, or questioned by, the external auditors, Finance or the Audit Committee
and that he needed to do nothing.

55. The detailed decisions as to the judgements made in respect of specific projects were

not taken at the level of CCS PRMs. In addition, routine decision-making regarding
management adjustments and trading was not made in CCS PRMs, but by way of the
process set out in the profit recognition policy. It was reasonable for Mr Howson to
rely on those processes and controls.

56. The criticism regarding the lack of minutes or records of CCS PRMs is of limited

significance given that discussion of financial performance at the CCS PRMs was by
exception only. Further, Mr Howson had good reason to consider the overall process
was operating as it should and, if minutes were not taken, that does not mean he knew
an appropriate record was not being made of any relevant judgement.

57. Receiving a detailed report does not equate to awareness of the figures in it. Mr

Howson was not expected to review the CCS PRM pack in advance of the meeting and
could not be expected to interrogate each individual reporting in the CCS PRM as to
whether they had covered every item that required his attention.

58. The PRM process was an important forum at which the financial performance

of projects was discussed and reviewed at different levels within CCS, often
in the context of Carillion’s budgeting and reforecasting process. At the CCS
PRMs, Mr Howson was informed of the deteriorating estimates by the Project
Teams for each of the Priority Contracts, the large and increasing divergence
from the traded figures for each project, and the correspondingly large and
increasing management adjustments applied to each project, such that the
traded figures remained unaltered. It was not reasonable for Mr Howson to
receive such information and take the view that, because this information was
not provided to him by way of the process set out in the profit recognition
policy, there was no need to take appropriate steps to satisfy himself that
such large and increasing management adjustments were warranted.

59. The lack of minutes taken of PRM discussions, and the lack of record of any

detailed review or changes to contract account judgements made or the
reasons for them, was a serious inadequacy in Carillion’s systems and
controls. Mr Howson attended CCS PRMs and must have been aware that
these matters were not properly recorded. As CEO, he had a responsibility to
work closely with the Group FD to ensure that there were appropriate internal
control processes, and it was not reasonable for him to assume that others
would make appropriate records.

60. The Authority considers that the evidence shows that Mr Howson was not just

provided with the CCS PRM packs, but that he attended many CCS PRMs during
the Relevant Period at which hard risk and other warning signs were
highlighted, including through presentations. Further, such presentations
were sometimes specifically sent to him in advance of the meeting. For
example, a presentation entitled ‘Profit Update Year End & Budget Reporting’
was sent to his personal email account, which was reserved for important
documents, in advance of the CCS PRM on 19 October 2016. Mr Howson must
therefore have been aware of the large and increasing financial risks and
potential exposures being reported by CCS.

Hard risk

61. Mr Howson accepts neither the alleged definition nor the alleged significance of hard

risk. The term was used inconsistently across Carillion. Mr Howson did not understand
hard risk to mean a sum to be written off. Instead, he understood hard risk to mean a
figure which might crystalise in the future if litigation went against Carillion.

62. The use of hard risk was something that Mr Howson had checked with Mr Adam was

an appropriate way of planning trading and managing risk. Mr Howson’s belief as to

the meaning and significance of hard risk is supported by the fact that others within
Carillion, including the Group FDs, did not share the Authority’s understanding. It
appears that neither the external auditors nor Finance considered that hard risk would
be a useful metric and it was not suggested to Mr Howson that hard risk posed a
potential threat to the accuracy of the Announcements.

63. It is unclear whether the email sent to Mr Howson on 18 March 2016 that described

hard risk as “not collectible” meant it was not collectable at all, or that the figure was
not collectable at that time.

64. The Authority considers that contemporaneous evidence shows that hard risk

was generally understood within CCS to be “the likely amount required to be
written off”. By receiving the email on 18 March 2016 which referred to sums
as “hard risk/not collectible”, Mr Howson must have appreciated at the very
least the risk that sums reported as hard risk were not genuinely collectable.
Mr Howson has not identified any contemporaneous document which
supports his submission regarding his understanding of hard risk.

65. In any case, irrespective of his and others’ understanding as to the precise

meaning of hard risk, Mr Howson was aware that hard risk was a type of risk
with a potentially significant impact on Carillion’s balance sheet and
profitability. He was also aware that the hard risks reported by CCS were very
large: they totalled £171.8 million for CCS in October 2016 and had increased
to £310.6 million by March 2017. As Mr Howson must have appreciated, they
were large not only in absolute terms, but also relative to Carillion’s
underlying PBT for 2016, which was £178 million. Further, he was aware that
hard risk was reported by CCS as part of the budgeting and reforecasting
process, a well-established and important process which formed the basis on
which CCS set out its expected financial performance for the year as assessed,
amongst other things, against market expectations. In those circumstances,
Mr Howson needed to take meaningful steps to understand, assess and
address the increasing levels and accumulated values of hard risk being
reported to him, but he did not do so.

The MCS

66. The MCS was not part of the PRM reporting process within Carillion and was not a

document which was used in PRMs. The figures did not consistently tie back to any of
the metrics relied upon by the business and it is not accepted that the figures were
reliable.

67. Mr Howson did not attend any of the MCRMs during the Relevant Period where the MCS

was discussed. He did not read the MCS and did not have knowledge of the likely
exposure figures. Nobody informed him that an issue had arisen at the October 2016
MCRM which required his attention. Receiving a detailed report does not equate to
awareness of the figures. In any case, MCSs were considered to be illustrative only.

68. The MCS was a report prepared for the purpose of a quarterly MCRM between

senior management at Divisional and Group level within Carillion. The MCS
section for CCS was compiled and submitted by senior directors: its Finance
Director and Commercial Director. The MCS records “exposure to traded
amount” by reference to best, likely and worst outcomes. The “likely”
exposures for CCS reported in the MCS totalled £159.9 million as at July 2016,
increasing to £431.9 million by May 2017. The size of these figures was a
clear and obvious warning sign, especially given their size relative to the
underlying £178 million PBT for the entire Carillion group for 2016.

69. The Authority does not consider it credible that Mr Howson did not read any

of the MCS documents during the Relevant Period. In particular, he was sent
the MCS in July 2016 and October 2016 to his personal email account, which
was filtered by his assistant and reserved for important documents, and he

was specifically forwarded another MCS by Mr Khan following the MCRM in
May 2017. He was also the effective chair of the MCRM and played a
significant role in it. The MCS provided an overview of the Group’s major
projects on a Group and divisional basis. This content would have been of
obvious interest to Mr Howson as the CEO, which is consistent with the fact
that he chaired the MCRM when available. The Authority therefore considers
it is inherently unlikely that he would have ignored MCS documents sent
specifically to him at his personal email address.

Negative accruals

70. Mr Howson had no knowledge of negative accruals until April 2017, and he did not

know the scale and significance of the problem until well after the May Announcement.
He took steps to ensure that the issue was properly investigated, which demonstrates
the implausibility of the allegation that he ignored potentially material issues of which
he was aware. His review and approval of the May Announcement was reasonably
predicated on an understanding that the financial aspects were appropriate given the
position taken by, for example, the Group FD. The steps taken included a review by
the external auditors, which concluded that no prior year restatement was necessary.
This is evidence of the factual position at the time and indicates the reasonableness of
his belief in the truth of the Announcements.

71. The Authority does not agree that any actions taken by Mr Howson in relation

to negative accruals supports his submission that he did not act recklessly in
the manner set out in this Notice. As explained above, the reasons for the
Authority’s conclusions that he acted recklessly relate to his failure to
respond appropriately to risks that he was aware of that the Announcements
were false or misleading and that Carillion did not have adequate procedures,
systems and controls to enable it to comply with its obligations under the
Listing Rules. Further, the Authority does not consider that the external
auditors’ conclusion that no prior year adjustment was necessary supports Mr
Howson’s submissions regarding his belief in the accuracy of the
Announcements, given Mr Howson’s knowledge, and the external auditors’
lack of knowledge, of the warning signs that he received in respect of the
deterioration in CCS’s financial performance.

Reporting to the Board and the Audit Committee

72. If there was inconsistency between the information and figures being presented to the

Board and the Audit Committee, and that presented to others at Carillion, Mr Howson
was not aware of it. It was the Group FD who reported on financial performance; it
was not Mr Howson’s responsibility and he was not responsible for deciding which
papers were provided to the Board.

73. Mr Howson reasonably considered that the Board was properly informed in light of the

procedures, systems and controls in place. As far as he was aware, the matters
reported to him and the Board in the Group FD’s Finance Report were the conclusion
of a well-constructed policy which included bottom-up reporting from the projects, with
reviews being undertaken according to the profit recognition policy. The Board had
three chartered accountants sitting on it at all times and could have requested other
information if it thought that was required.

74. The Audit Committee was meant to ensure that Carillion had proper internal controls

and an effective control environment, and to review the integrity of the financial
statements. It was chaired by a Non-Executive Director who was an accountant. Whilst
Mr Howson attended Audit Committee meetings, the Audit Committee would meet the
Group FD and separately the external auditors without Mr Howson being present. Mr
Howson was not responsible for what was reported to the Audit Committee.

75. The roles of the Audit Committee and the external auditors shows that there were

substantial checks, controls and validation processes in place for the judgements that

were made. If the Audit Committee considered that there was important information
that it had not received, it would have requested it.

76. Mr Howson received the management information produced and reported by

CCS which highlighted large and increasing risks associated with the reported
financial performance of CCS’s construction projects during the Relevant
Period, as well as the reports which went to the Board and the Audit
Committee which contained much more optimistic assessments of the
financial performance of those projects. Accordingly, Mr Howson must have
been aware of the inconsistency between the figures in these different
reports. Mr Howson’s responsibilities as CEO included working closely with
the Group FD to ensure that Carillion communicated effectively with investors
and had appropriate internal control processes. Given the warning signs of
which he was aware, it was not reasonable for Mr Howson to fail to bring them
to the attention of the Board and the Audit Committee, in circumstances
where they were not mentioned in the papers provided to them. Mr Howson’s
failure to do so meant that the Board and the Audit Committee were seriously
hampered in providing effective oversight of CCS’s financial performance and
the contract accounting judgements being applied to its major projects.

77. Although the Board and the Audit Committee could have asked for further

information, the materials before them did not disclose the hard risks, MCS
reports and other warning signs of which Mr Howson was aware. It was not
reasonable for such information to be held only at executive director level,
which meant that the Board and the Audit Committee were not in the position
to ask questions about such matters.

MPSRs and Overtrade Reports

78. Mr Howson believed that the source of the financial information in the MPSRs was

derived from a combination of the Contract Appraisals and any agreed management
adjustments, which followed the profit recognition policy and reflected the accounting
judgements reached as to the traded positions. He reviewed and approved the MPSRs
on the basis that other senior management (including the Group FD) were content with
the figures. As CEO it was not his responsibility to conduct a detailed review and
comparison of the underlying supporting documents.

79. Mr Howson does not accept that receiving the Overtrade Report meant that he knew

any necessary constitutive fact of any alleged contravention.

80. MPSRs and Overtrade Reports were two key reports received by the Board

dealing with the financial performance of CCS’s projects. Neither report
showed
the
financial
risks
associated
with
increasing
management

adjustments, hard risks, MCS exposures, divergences from budgeted
forecasts for major projects or variances to peer review recommendations.
Instead, they identified much lower levels of risk associated with contract
accounting judgements.

81. Mr Howson was aware that the financial information in the MPSRs was

inconsistent with the hard risk and MCS figures and with the Project Teams’
assessments of the financial performance of the Priority Contracts. In those
circumstances, it was not appropriate for him to review the MPSRs, and
approve the figures in them, on the basis that other members of senior
management were content with the figures. Instead, he should have made
enquiries about the inconsistencies and brought them to the attention of the
Board and the Audit Committee.

82. Mr Howson understood that the Overtrade Report was regarded within

Carillion as an important indicator of the amount of revenue (subject to
contract accounting judgements) that was being recognised in Carillion’s
management accounts at a particular point in time. He knew the figures

reported in the Overtrade Report did not identify hard risks, exposures
reported in the MCS or divergences from budgeted forecasts in the financial
performance of certain major projects, and therefore that the Board was not
informed of information that was highly relevant to its deliberations.

The role of the external auditors

83. External auditors were retained by Carillion to identify (among other things) that the

internal controls, including reporting procedures, were working properly, and that the
financial statements as a whole were free from material misstatement.

84. The external auditors’ role, knowledge and power to obtain documents and

information, combined with their opinion that the financial statements gave a true and
fair view of the state of Carillion’s affairs for the purposes of the December
Announcement, were objective facts which are relevant to whether the documents
relied upon establish Mr Howson’s knowledge of the alleged breaches.

85. The fact that the external auditors did not identify any of the issues relied on means

the Authority should be cautious in concluding that Mr Howson, who is not an
accountant, had in fact identified such matters or that he was reckless in not doing so.

86. The external auditors’ role in respect of the financial statements does not

negate Mr Howson’s own primary responsibilities, as a director, for the
preparation and approval of the financial statements and ensuring that they
were ‘true and fair’. The responsibility of the external auditors only extended
so far as to provide an opinion on whether the financial statements were ‘true
and fair’, not to ensure that they were. Having received warning signs
regarding CCS’s financial position, Mr Howson needed to take action to
discharge his responsibilities. He could not reasonably disregard these
warning signs on the ground that he expected the external auditors to
uncover the same matters, in particular in circumstances where he was aware
that the Audit Committee was not informed of any of them.

The Priority Contracts

87. Mr Howson did not know facts which indicated that the financial performance of the

Priority Contracts in CCS was deteriorating more than the figures presented to the
Board and the Audit Committee would suggest. The case against him is based on
figures cherry-picked from about 10 documents across a year, amongst a large volume
of other material that Mr Howson received. He did not even see some of those figures
and did not understand the meaning or significance ascribed to any of the figures. He
relied on the expertise and judgements made by others, and nobody ever identified to
him that the figures meant that there should be an adjustment to the traded figures.

88. The Priority Contracts were four out of 40 or 50 major projects in CCS. Mr Howson

could not be expected to “know” all the information he was sent, especially if it related
to a sphere of operation that was not his responsibility. He received a large amount of
material and the allegedly divergent figures that he did receive were contained within
a mass of other information and/or not identified as requiring his attention and/or
related to a discussion at a meeting that he did not attend. Given Carillion’s size and
complexity, he could not have been reasonably expected to know all material facts
about each of Carillion’s various contracts.

89. In respect of the deterioration in the financial performance of the Priority Contracts,

the management adjustments that were being applied and how the matters were
treated in the accounts were not decisions for Mr Howson. The fact that the
management adjustments had increased does not mean the adjustments were
improper. If adjustments were being applied to maintain an unjustified forecast profit
margin improperly, Mr Howson was not aware of that practice.

90. The alleged divergence in the figures in the graphs for the Priority Contracts in Section

G of the Notice is unfair, as the comparison that is being made is not between like-for-

like figures. The negative figures that are being compared in the graphs are not the
considered site view post-management adjustments. They were either site view
figures prior to the management adjustment or a different metric that was not intended
to represent the post management adjustment figure. Overall, the graphs do not show
that Mr Howson was aware that the figures being presented to the Board and/or the
Audit Committee were wrong.

91. Mr Howson was informed by a variety of means of large and increasing

divergences between the assessments of financial performance by the Project
Teams and/or management teams within CCS and the financial performance
as reflected in Carillion’s budgeted forecasts. The information he received
included being told of: very large disparities between the end of life estimates
provided by experienced CCS personnel and the much more positive
assessments reflected in Carillion’s budgeted forecasts; assessments from
within CCS which explicitly set out itemised recovery plans running to tens of
millions of pounds, and even after the application of those proposed
recoveries still concluded that the contracts in question were severely loss-
making; and assessments not just from Project Teams but also from CCS
management and director level, which could not just be considered to be site
view estimates. RLUH, Battersea and MMH were reported to the Board as
profit-making contracts throughout the Relevant Period. As Mr Howson was
aware, if they were actually loss-making contracts, the full extent of the loss
needed to be recognised immediately in the accounts by way of an
appropriate write down under IAS 11. In those circumstances, Mr Howson
should have treated the information he received indicating that the contracts
were loss-making with the utmost seriousness, due to the significant impact
of the losses having to be recognised in full immediately.

92. AWPR was reported to the Board as a profit-making contract until October

2016, whereupon it was adjusted to an end of life loss of £10 million. Mr
Howson was repeatedly informed that the best end of life assessment for
AWPR was a far greater loss. These warning signs concerning AWPR were
extremely serious given the loss-making nature of the contract: the full extent
of the loss needed to be recognised in the accounts immediately under IAS
11, with a correspondingly significant impact on Carillion’s accounts for 2016.

93. The scale of the divergences highlighted to Mr Howson was considerable and

the Authority considers that they are fairly illustrated by the graphs contained
in Section G of this Notice. Carillion’s financial results for 2016 were based
on an underlying PBT figure of £178 million for the entire Group, yet the
divergences highlighted to Mr Howson, even in respect of a single project,
consistently ran into tens of millions of pounds, and equated to a very
substantial proportion of the underlying PBT for the whole Group. In those
circumstances, it was imperative that Mr Howson treated the figures with the
utmost seriousness, and so the Authority does not accept that it was
reasonable for him not to pay due attention to the Priority Contracts on
account of all the other information he received.

94. The management adjustments were so large that Mr Howson could not simply

trust that they were appropriate. However, he did not make any enquiries to
satisfy himself that management adjustments of such scale were warranted.
He also did not inform the Board or the Audit Committee of any of the warning
signs he received, notwithstanding that the Board emphasised at the
December 2016 Board meeting that it was relying on the judgement of the
executive and that it was “important to understand whether the trading
performance of the business had deteriorated”.

The Announcements

95. Mr Howson was not aware there was a risk that the Announcements were false or

misleading and he did not consider them to be false or misleading. He reviewed and
approved the Announcements from his perspective as CEO. He did not draft them and
it formed no part of his role to make any relevant accounting judgements. The Group
FD was responsible for the drafting process and, if there was an issue with the figures,
he should have raised it. That is also the case in respect of anyone from CCS who
thought that there was an issue.

96. Mr Howson had good reasons to consider that the Announcements were true. These

included that the financial aspects were the culmination of a process that carried with
it the express or implied endorsements of various well-qualified persons who Mr
Howson trusted: those responsible for making, reviewing and approving the
judgements within CCS; the Finance function; the Group FD; the Audit Committee;
and the external auditors.

97. The reference in the May Announcement to “particularly in our international markets”

did not mean exclusively restricted to those markets.

98. Mr Howson played an integral role in the preparation of the Announcements

and approved them as a Board member. He therefore had important personal
responsibilities in respect of the Announcements, but he did not take
appropriate action to address the warning signs that he received or bring
them to the Board’s or the Audit Committee’s attention. In the face of these
warning signs, and given his responsibilities, Mr Howson should not have
relied on others to raise concerns with the figures and should have taken all
reasonable steps to satisfy himself that the Announcements were accurate
and not misleading.

99. Mr Howson was aware that the Announcements made positive statements

about Carillion’s performance generally and in relation to CCS’s construction
business segment in particular. He was also aware that these positive
statements were inconsistent with significant financial risks and exposures
which had been brought to his attention through numerous warning signs,
and which he was aware had not been addressed or brought to the attention
of the Board or the Audit Committee. In these circumstances, the Authority
considers that Mr Howson was aware that there was a risk that the
Announcements were false or misleading.

100.
The comment in the May Announcement regarding managing challenging

contract positions was explicitly linked to international markets and did not
refer to the UK, so was not sufficient to provide an accurate depiction of the
Group’s trading as at the date of the May Announcement. The comment was
expressly linked to the similar statement made in the March Results
Announcement, which was specific to the Middle East and Canada, and did not
convey significant problems within Carillion’s UK construction business (i.e.
CCS).

101.
The Authority is not permitted to impose a financial penalty in respect of Mr

Howson’s alleged knowing concern in the alleged breaches of LR 1.3.3R, Listing
Principle 1 and Premium Listing Principle 2 because the Warning Notice was not issued
within three years of the date on which the Authority had information from which the
alleged misconduct could reasonably be inferred.

102.
The matter was referred to the Authority’s Enforcement division on 25 September

2017 by way of an Investigation Recommendation which was based on information
held by the Authority over three years before 18 September 2020, the date the
Warning Notice was issued. Annex 1 to the Investigation Recommendation stated that

Mr Howson was under consideration for investigation and potentially implicated in the
misconduct. The Authority therefore had sufficient knowledge to justify an
investigation prior to 18 September 2017, and so, having regard to the Tribunal’s
decision in the case of Jeffery7, the Authority is time-barred from imposing a financial
penalty on Mr Howson in respect of those alleged breaches.

103.
The Authority does not agree that it is time-barred from imposing a

financial penalty in respect of the breaches of LR 1.3.3R, Listing Principle 1
and Premium Listing Principle 2. Section 91 of the Act requires the Authority
to issue a warning notice within three years of the date on which it first knew
of a breach of the Listing Rules or had information from which it could
reasonably be inferred. Pursuant to Jeffery, the correct approach to the issue
of limitation is “first, to determine what the misconduct is that the Authority
contends that [the person] is guilty of, and secondly to determine the earliest
date on which the Authority knew of the misconduct or had information from
which the misconduct could reasonably be inferred.”

104.
In summary, the particular misconduct alleged against Mr Howson, as set

out in the Warning Notice given to him (and repeated in this Notice), is that
he was knowingly concerned in breaches by Carillion of LR 1.3.3R, Listing
Principle 1 and Premium Listing Principle 2. This is as a result of his failure
to act in response to numerous warning signs highlighting financial risks and
exposures associated with contract accounting judgements made within CCS,
for example by failing to bring these matters to the attention of the Board and
the Audit Committee and by failing to ensure that the content of the
Announcements appropriately reflected them. As at 18 September 2017 (i.e.
three years prior to the Warning Notice was issued), the Authority did not
have information concerning any of the warning signs identified in the
Warning Notice or Mr Howson’s failure to respond appropriately to them.
Accordingly, the Authority did not have information from which Mr Howson’s
breaches could reasonably be inferred.

105.
Further, the Authority notes that the decision to refer the matter to the

Authority’s Enforcement division on 25 September 2017 only concerned
Carillion as a firm and not Mr Howson as an individual. Notwithstanding that
Annex 1 mentioned Mr Howson as an individual under consideration for
investigation, the Investigation Recommendation stated that the Authority
did not have “sufficient information to establish whether any of the directors
were knowingly concerned and or responsible for the alleged breaches”.

Financial penalty

106.
Mr Howson’s primary position is that he was not in breach and so no financial

penalty should be imposed. Notwithstanding his primary position, at Step 2 of the
financial penalty calculation, the assessment of the seriousness level should take into
account that steps were taken to ensure compliance, that Mr Howson acted promptly
when alerted to issues, and that he was entitled to place some reliance on Finance and
the external auditors.

107.
In respect of the calculation of the income figure, Mr Howson does not agree the

benefits figure because it includes allowances related to his work which should not
form part of the salary calculation. He also does not agree the pension figure, which
is too high. In addition, he disputes the calculation of the long-term incentives “LEAP”
award shares; it should be zero as the shares were received outside the Relevant
Period (in October 2017), or an amount which reflects the lower value of the shares at
the time of receipt.

7 Andrew Jeffery v the Financial Conduct Authority: FS/2010/0039

108.
For the reasons given in this Notice, the Authority considers that Mr

Howson was knowingly concerned in breaches by Carillion and that he acted
recklessly. The Authority considers it appropriate to impose a financial
penalty on Mr Howson in respect of his misconduct.

109.
The factors that the Authority considers relevant to the seriousness level

at Step 2 of the penalty calculation are set out in paragraphs 6.9 to 6.12 of
this Notice. The Authority considers that the factors mentioned by Mr Howson
do not take account of his responsibilities, including in relation to Carillion’s
risk management and internal control processes, and his integral role in
approving the Announcements, and do not affect the seriousness level.

110.
The Authority has used the information provided in the Remuneration

Report in Carillion’s 2016 Annual Report and Accounts, extrapolated into
2017, as the basis for the calculation of Mr Howson’s income figure, including
the benefits and pension figures. The Authority considers this is the fairest
approach, in the absence of any documentary evidence to the contrary. The
Authority has also used the Remuneration Report to determine the LEAP
award figure. The Authority considers this to be appropriate as the award is
treated in the Remuneration Report as being earned in 2016.

The Authority’s investigation

111.
The Authority’s Enforcement division failed in its investigation to interview key

personnel and to obtain relevant information, including documentation used by the
external auditors for the purposes of their audit. It also preferred the interview
evidence of certain employees over others for no good reason and failed to press
interviewees in questioning on certain important matters.

112.
It was also procedurally unfair for the Authority’s Enforcement division to introduce

new evidence after the issue of the Warning Notice. The Authority should not make
any adverse findings against Mr Howson on the basis of the new material.

113.
The Authority does not accept that the Enforcement division should have

carried out more interviews. In respect of the individuals mentioned by Mr
Howson, the Enforcement division obtained and reviewed evidence of
interviews carried out by other regulators. The Authority has also paid due
regard to all the evidence before it in reaching its decision.

114.
The Authority does not consider it was necessary or appropriate for the

Enforcement division to investigate the adequacy of the audit carried out by
the external auditors in order to reach conclusions regarding the
appropriateness of Mr Howson’s conduct, in particular given Mr Howson’s
responsibilities, role in the Announcements and awareness of warning signs
that the external auditors were not aware of. Further, the Enforcement
division did obtain relevant documents from the external auditors for the
purposes of its investigation and, in the light of Mr Howson’s representations,
identified and disclosed further relevant documents.

115.
Mr Howson was given the opportunity to make, and did make, further

written representations in respect of the new material produced by the
Enforcement division following the issue of the Warning Notice. He also made
oral representations following the disclosure of the new material. In the
circumstances, the Authority considers that Mr Howson has been given a
reasonable opportunity to make representations in respect of this new
material and that it is not unfair for the Authority to have regard to this
material in reaching its decision.


© regulatorwarnings.com

Regulator Warnings Logo